    The first stage of the Berwyndale South Project is currently 49% complete, on budget and on
    track to deliver first gas to CS Energy by 1 April 2006. QGC has a 10-year contract with
    CS Energy to supply 4 petajoules (PJ) of gas a year from Berwyndale South, with first
    deliveries no later than 31 July 2006; and another 10 year contract to supply 4PJ of gas per
    year from Berwyndale South to Braemar Power Partners commencing 1 October 2006. There
    is provision to provide early gas under both contracts.

    Monthly Reporting
    QGC is committed to keeping the market informed of progress on its operations. In line with this
    commitment, QGC will provide a status report to the market on the first Monday of each month
    during the development and commissioning of the Berwyndale South Gasfield in Queensland’s
    Surat Basin.
    DRILLING
    Despite heavy rain in the region, the drilling program is currently on schedule with 10 of 25
    wells drilled and 4 wells completed. During the planning phase, QGC took the precautionary
    measure of ensuring all well sites had all-weather access. This proved for the drilling program
    as the Surat Basin experienced the wettest October since 1972.
    QGC has achieved an average drilling cycle of 6.5 days per well and is working to reduce it to 5
    days per well. Figure 1 shows the reduction in drilling time for the first six development wells at
    Berwyndale South.

    PRODUCTION
    Four wells are currently on-line and flowing gas. These flow rates are well above the Banker’s
    Case proportions for the project and point to lower development costs. (Figure 2 shows the
    conservative Banker’s Case compared with current gas flows from the wells on production).
    Two of the wells (#36 and #37) were completed using an all-Walloon completion technique
    which accesses all six of the Juandah and Taroom coal seams. These are the first two wells at
    Berwyndale South to have been completed in this manner and the resulting gas flow rates have
    exceeded expectations. Berwyndale South #36 has improved gas production to a weekly
    average of 199,000 cfd, and Berwyndale South #37 is producing at a weekly average of
    126,000 cfd.
    By achieving higher than expected gas flow rates and successfully extracting gas from all
    target seams in each well, QGC expects to reduce development costs by 10 to 20%, because
    fewer wells will be needed to produce the required gas.

    FIELD GATHERING
    Work on the field gathering system is well ahead of schedule. This work has involved some
    2,000 welds over a period of 3 months. Welding on the water gathering pipelines is
    substantially complete and welding on the gas gathering pipe is expected to be complete at the
    end of this week. The remaining work on the field gathering system involves digging in the
    pipework.
    Reverse osmosis trial
    Equipment for the 10-week reverse osmosis trial was delivered to site on 30 November 2005
    and is now operational. Subject to the results of this trial and the availability of Federal
    Government funding, a full scale reverse osmosis plant will be installed at Berwyndale South to
    supply Chinchilla Shire Council with 1,000 megalitres of drinking water per year.

    CENTRAL TRANSPORTATION INFRASTRUCTURE
    Screw compressors
    Three screw compressors arrived in Brisbane on Sunday 27 November 2005 and were
    delivered to site the following day. The compressors and their respective coolers were set in
    place on Tuesday 29 November 2005 using two 80 tonne cranes. The lifts had been planned to
    take two days but were accomplished over one day.

    Reciprocating compressors
    The first two reciprocating compressors are between Panama and Brisbane. This shipment is
    expected to arrive in Brisbane on 18 December 2005. The third compressor (which will service
    the Braemar contract) has been shipped from Galveston, Texas to Manzanillo, Panama on 27
    November 2005 (USA time), arriving in Australia on 2 January 2006.
    TEG Dehydration Units
    In Canada, Moody International and Transera are progressing final inspection of TEG
    Dehydration Units prior to shipment. The units are expected to arrive in Australia on 15 January
    2006.

    Windibri Pipeline
    The pipeline crew has been mobilised for the Windibri Export Pipeline, which will link
    Berwyndale South with the Roma to Brisbane Gas Pipeline. Pipe has been shipped by train to
    Brisbane and deliveries to site will commence today.
    The pipeline contractor commenced Right of Way clearing on Tuesday 22 November 2005.
    Approximately 9 kilometres of the route had been cleared by Sunday 27 November 2005. The
    contractor is now preparing for delivery of the pipeline to site and installation. (A map showing
    the route of the Export Pipeline is included as Figure 3)
    The alignment survey for the trunkline which will connect the screw compressors to the main
    plant was completed and the design progressing.

    MYALL CREEK EAST
    In late November, Origin Energy announced large commercial gas flows from Basal Rewan
    Sandstone in Myall Creek #1. QGC has a 50% interest in the adjacent Block 2656
    approximately 4km northeast of the Myall Creek Gasfield and 7km northeast of the Churchie
    Gasfield.
    QGC and joint venturer Origin Energy drilled Myall Creek East #1 in September 2003 but there
    remains some doubt about the status of this hole which was plugged. The parties have been
    considering drilling a second hole in the vicinity of Myall Creek East #1.
    The recent drilling success at Myall Creek has raised the expectations for the Myall East area
    as well. Gas from this area could be readily connected to the existing gathering, infrastructure
    and major trunkline systems.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.