13th October 2008
MUNALI NICKEL PROJECT UPDATE
KEY POINTS
• First revenue from sale of concentrates received.
• Appointment of new General Manager – Munali.
• Final completion of construction contract achieved and construction
contractor demobilised from site.
• Commissioning of the processing plant is progressing well with 900ktpa
(2,465tpd) nameplate capacity being exceeded on a number of occasions.
• Dedicated power line to Project completed and energised.
• Mining development rates on target, stoping operations commenced.
• Final draw-down of US$10m – Barclay’s senior debt facility.
- Forums
- ASX - By Stock
- ALB
- munali nickel project update
munali nickel project update
Featured News
Add ALB (ASX) to my watchlist
|
|||||
Last
5.7¢ |
Change
0.000(0.00%) |
Mkt cap ! $3.720M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 9803 | 5.1¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
5.7¢ | 20000 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 9803 | 0.051 |
1 | 379817 | 0.050 |
1 | 200000 | 0.040 |
1 | 38499 | 0.026 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.057 | 20000 | 1 |
0.059 | 120000 | 1 |
0.065 | 26667 | 1 |
0.077 | 24875 | 1 |
0.079 | 38053 | 2 |
Last trade - 16.12pm 25/07/2024 (20 minute delay) ? |
Featured News
ALB (ASX) Chart |
Day chart unavailable