Hi IFINO,
No need to be negative....its your calcs that are out. They spudded June 1 so 45 days to yesterday's 3400m (sub sea) is 75.55m/day...which is fairly respectable with 2170m of water.
Original total planned well time was 79 days to Fan 2 lower Jurassic (approx. 5600m). Of course I don't have Planned Vs Actual but I'm guessing the well might be 5-8 days over at this stage. This time can be made up in the lower parts of the hole (depending on casing design) but at this stage I don't see a big issue with progress.
Cheers,
Cheers,
- Forums
- ASX - By Stock
- MZ-1
Hi IFINO, No need to be negative....its your calcs that are out....
-
- There are more pages in this discussion • 6 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
NEWS
Breakthrough programs slash healthcare events, driving a significant A$1.8M+ annual revenue boost
NEWS
Antler Copper Project hits major permitting milestone – air quality permit advances to final review
Add HHR (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.7¢ |
Change
0.001(8.33%) |
Mkt cap ! $18.25M |
Open | High | Low | Value | Volume |
0.6¢ | 0.7¢ | 0.6¢ | $2.843K | 472.8K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
16 | 19621686 | 0.6¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.7¢ | 32133315 | 24 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
15 | 19461686 | 0.006 |
24 | 6029943 | 0.005 |
9 | 5152500 | 0.004 |
3 | 3816666 | 0.003 |
4 | 7200000 | 0.002 |
Price($) | Vol. | No. |
---|---|---|
0.007 | 32028188 | 23 |
0.008 | 6096070 | 7 |
0.009 | 2250000 | 4 |
0.010 | 1360000 | 7 |
0.011 | 743000 | 1 |
Last trade - 11.10am 04/10/2024 (20 minute delay) ? |
Featured News
NEWS
Breakthrough programs slash healthcare events, driving a significant A$1.8M+ annual revenue boost
CC9
Chariot Corporation (ASX:CC9) refines Black Mountain strategy, launching Pilot Mine to seize U.S. lithium opportunity
HHR (ASX) Chart |