KEY 0.00% 0.1¢ key petroleum limited

new ann out

  1. 3,805 Posts.
    lightbulb Created with Sketch. 188
    21 February 2013
    The Manager
    Australian Securities Exchange
    Company Announcements Office
    Level 4/20 Bridge Street
    SYDNEY NSW 2000
    Dear Sir
    RE: DRILLING UPDATE FOR CYRENE-1 IN EP 438, CANNING BASIN, WESTERN AUSTRALIA
    FOR THE PERIOD 0600 HOURS 12 FEBRUARY 2013 TO 0600 HOURS 21 FEBRUARY 2013
    Please find details of the drilling activities of Cyrene-1 attached.
    Buru Energy Limited 37.5%
    Mitsubishi Corporation (Diamond Resources (Canning) Pty Ltd) 37.5%
    Key Petroleum Ltd (Gulliver Productions Pty Ltd) 20.0%
    Indigo Oil Pty Ltd 5.0%
    Regards
    KANE MARSHALL
    Managing Director
    KEY PETROLEUM LIMITED
    Key Petroleum Ltd
    Ground Floor, 39 Stirling Highway, Nedlands WA 6009
    T: +61 (0) 8 6389 0322 F: +61 (0) 8 6389 0697 E: [email protected] W: www.keypetroleum.com.au
    ABN 50 120 580 618

    ASX AND MEDIA ANNOUNCEMENT
    21 February 2013
    DRILLING REPORT FOR CYRENE-1 IN EP 438, CANNING BASIN, WESTERN AUSTRALIA
    FOR THE PERIOD 0600 HOURS 12 FEBRUARY 2013 TO 0600 HOURS 21 FEBRUARY 2013
    Since the last report issued at 0600 hrs 12 February 2013, DCA Rig 7 has completed all coring and logging of
    the Goldwyer Formation to 1022m RT (rotary table). The 7” casing required to isolate the Goldwyer and other
    formations in the 8 ½” hole have now been run in the hole and cemented.
    The completion of coring in 8 ½”corresponded with consistent oil shows across the lower Goldwyer Formation
    and background gas up to 5 units in the lower part of the Goldwyer. These results are consistent with the
    drilling of the Goldwyer to date, indicating that the Goldwyer Formation is a good source rock for generating
    oil in this part of the Canning Basin.
    All necessary BOP testing to drill ahead in the 6” hole section were completed and drilling has now been
    completed into the Willara Formation conventional oil objective with total depth (TD) called at 1070m RT.
    Background gas was observed to be between 5 and 10 units with some oil shows observed through the
    Willara sequence. The forward plan is to run wireline logs and then conduct a drill stem test in the 6” hole to
    fully evaluate the Willara Formation. The purpose of the flow test is to establish the true formation fluid in the
    Willara Formation (water or oil) and if any hydrocarbons are present, whether they can flow at economic
    rates.
    The next ASX release will be made when the Willara Objective has been fully evaluated or if there is a material
    event to report.
    For media and shareholder enquiries please contact [email protected]
    Kane Marshall
    BSc (Geology), BCom (Inv & Corp Fin), Masters PetEng, SPE, AAPG, PESGB, SPWLA
    Managing Director
    Key Petroleum Ltd
    Telephone: +61 8 6389 0322
    Competent Persons Statement
    Information in this ASX Release relates to information compiled by Mr Kane Marshall. Kane Marshall is a Practicing Petroleum Engineer and holds a BSc (Geology), a BCom
 
watchlist Created with Sketch. Add KEY (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.