    In their Jan14 filing, they stated construction would commence mid 2015 with production 3Q18. However, their revised timeline below states construction Oct16 and full commencement late 2019, which is ~12 months after MLNG.

    Of more immediate interest is their Jan14 ann. of a global tender (outsourced) for tolling parties for 5mtpa. As yet, no TAs ann. Nonetheless, worth watching to see how this does progress.

    Project Timeline (Anticipated)
    October 2014: FERC Pre-filing Letter submitted and FERC issues Notice of Pre-Filing Commencement
    December 11, 2014: Public Open House in Cameron
    August 2015: Project files Application with FERC
    June 2016: FERC issues final Environmental Impact Statement
    September 2016: FERC issues Order issuing Certificate and Granting Section 3 Authority
    October 2016: FERC issues Authorization to Proceed and construction begins
    December 2018: In Service – Partial Commencement of Operations
    Late 2019: Full Commencement of Operations