Expanding on the post by YA.
Quick Translation:
Water depth = 143m (site dependent)
Ocean Patriot Rotary Table (RT) = approx 26m after ballast down.
RT to sea bed = 169m.
- Drill 36" hole from 169 to 213m ? Riserless (No blow out protection)
- Run and cement 30? casing
- Drill 26" hole from 213 to 310m ? Riserless
- Run and cement 20? casing
- Drill 17.5" hole from 310 to 350m
- Run 13 3/8? casing (at this point they'll install the BOP & do the usual pressure testing b4 commencing drilling to TD.
- Drill 8.5" hole to TD of 826m. Next thing you know old Jeds a Billionare?
Unless they run in to issues this should be very quick. 30 days will only be needed if there is a well test following any discovery.
Also, anyone claiming there has not been enough ?community consultation? should have a look at the extensive list on the website (posted by YA) under the heading CONSULTATION.
- Forums
- ASX - By Stock
- MMR
- new seaclam-1 drill program
new seaclam-1 drill program, page-5
-
- There are more pages in this discussion • 9 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add MMR (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.4¢ |
Change
0.000(0.00%) |
Mkt cap ! $3.236M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
MMR (ASX) Chart |
Day chart unavailable
The Watchlist
3DA
AMAERO INTERNATIONAL LTD
Hank Holland, Executive Chairman and CEO
Hank Holland
Executive Chairman and CEO
SPONSORED BY The Market Online