Aug 22 (Reuters) - Allkem Ltd (AKE) :
- FY CONSOLIDATED NET PROFIT AFTER TAX FROM CONTINUING OPERATIONS OF US$524.6 MILLION
- FY GROUP REVENUE OF US$1,207.8 MILLION ACHIEVED
- SAL DE VIDA CONSTRUCTION IS WELL UNDERWAY, AND JAMES BAY IS ADVANCING WITH APPROVALS RECEIVED BY THE FEDERAL GOVERNMENT FOR THE ESIA
- OLAROZ STAGE 2 ACHIEVED FIRST WET PRODUCTION IN MID-JULY WITH COMMISSIONING TO CONTINUE AND RAMP UP OVER NEXT 12-18 MONTHS
- MT CATTLIN'S ORE RESERVE UPDATE CONFIRMED AN ADDITIONAL 4-5 YEAR MINE LIFE TO 2027-2028
- FEDERAL APPROVAL FOR JAMES BAY ESIA WAS OBTAINED IN JANUARY 2023 AND A NEW HIGH-GRADE ZONE OF MINERALISATION WAS IDENTIFIED
- HAVE DETERMINED THAT THERE WILL BE NO PAYMENT OF A DIVIDEND FOR YEAR
- NARAHA LITHIUM HYDROXIDE PLANT ACHIEVED FIRST PRODUCTION