Dec 20 (Reuters) - BCI Minerals Ltd (BCI) :
- PROVIDES MARDIE PROJECT UPDATE
- CONSTRUCTION OF 36-BED ACCOMMODATION VILLAGE COMPLETE , CONSTRUCTION OF LARGE-SCALE TRIAL POND PLANNED TO START IN Q1 2020.
- REVISED ENVIRONMENTAL REVIEW DOCUMENT WILL BE RE-SUBMITTED IN EARLY 2020
- FINAL INVESTMENT DECISION SCHEDULED FOR Q3 2020, AND FIRST CONSTRUCTION BY EARLY 2021
Dec 20 (Reuters) - BCI Minerals Ltd (BCI) : PROVIDES MARDIE...