April 8 (Reuters) - Australia's Beach Energy (BPT) said on Monday it expects the first gas production from its Waitsia Stage 2 gas project in early 2025, instead of mid-2024, due to further quality issues.
The oil and gas explorer also raised its total capital expenditure estimate for the project to between A$600 million ($394 million) and A$650 million, from an earlier estimate of A$400 million to A$450 million.
"Having to redirect existing onsite labour to remedial works is slowing the progress of pre-commissioning activities, resulting in further delay and cost increases," said Managing Director and CEO Brett Woods.
The gas project, a joint venture with a unit of Japanese firm Mitsui & Co 8031.T , was initially due to start producing gas for export through the North West Shelf liquefied natural gas (LNG) plant in late 2023, Beach said in May last year.
($1 = 1.5223 Australian dollars)
- Forums
- ASX - By Stock
- BPT
- News: BPT UPDATE 1-Beach Energy delays Waitsia Stage 2 gas production, hikes project cost
News: BPT UPDATE 1-Beach Energy delays Waitsia Stage 2 gas production, hikes project cost
-
- There are more pages in this discussion • 1 more message in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add BPT (ASX) to my watchlist
(20min delay)
|
|||||
Last
$1.31 |
Change
0.025(1.95%) |
Mkt cap ! $2.977B |
Open | High | Low | Value | Volume |
$1.30 | $1.31 | $1.29 | $12.66M | 9.749M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 6390 | $1.30 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$1.31 | 211309 | 8 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 6390 | 1.300 |
4 | 39961 | 1.295 |
11 | 176936 | 1.290 |
11 | 171386 | 1.285 |
10 | 143558 | 1.280 |
Price($) | Vol. | No. |
---|---|---|
1.305 | 211309 | 8 |
1.310 | 314066 | 12 |
1.315 | 422894 | 9 |
1.320 | 251551 | 11 |
1.325 | 510136 | 10 |
Last trade - 16.10pm 27/08/2024 (20 minute delay) ? |
Featured News
BPT (ASX) Chart |
The Watchlist
SBW
SHEKEL BRAINWEIGH LTD
Dani Nadri, Country Manager Australia
Dani Nadri
Country Manager Australia
SPONSORED BY The Market Online