That sort of timetable would definitely require another large capital raising.
There is a limit to how quick NextDC can move. Going off the DA plans for S2. The schedule has it opening with a "Temporary Supply Substation" (usually 11kV) prior to 33kV utility supply being provisioned.
This could see them limited to <10MW. Could be a good question to ask at the AGM, when is the 33kV supply likely to be commissioned to site.
It's been mentioned by management that its 6-9months to make additional data halls available (though can be done concurrently to speed up).
From memory, S1/M1 had a developed capital cost ~$10M/MW (excluding building).
- Forums
- ASX - By Stock
- NXT
- NextDC buys new site in Sydney
NXT
nextdc limited
Add to My Watchlist
1.09%
!
$14.41

NextDC buys new site in Sydney, page-5
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
$14.41 |
Change
0.155(1.09%) |
Mkt cap ! $9.212B |
Open | High | Low | Value | Volume |
$14.28 | $14.45 | $14.19 | $10.33M | 720.4K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
23 | 1516 | $14.40 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$14.41 | 924 | 13 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
22 | 1393 | 14.390 |
18 | 2799 | 14.380 |
12 | 1523 | 14.370 |
8 | 2487 | 14.360 |
9 | 3837 | 14.350 |
Price($) | Vol. | No. |
---|---|---|
14.400 | 496 | 13 |
14.410 | 3743 | 23 |
14.420 | 4960 | 23 |
14.430 | 2925 | 12 |
14.440 | 3572 | 14 |
Last trade - 13.26pm 26/06/2025 (20 minute delay) ? |
Featured News
NXT (ASX) Chart |
The Watchlist
3DA
AMAERO LTD
Hank Holland, Chairman & CEO
Hank Holland
Chairman & CEO
Previous Video
Next Video
SPONSORED BY The Market Online