    Hi Voose , I would be asking management some questions .

    These figures are from the only PFS that I could find that GPX has done, good luck relying on these if this PFS is all that GPX has done so far ? a DFS will more accurately and independently reflect the viability of the project , the more detailed BFS will be required to justify financing the project.

    It's near impossible to get an average 10.6 TGC head grade during plant feed for 8.5 years when the best grade you have is 10.6% TGC ? with a cut off of 5%TGC ? this blows out all the figures below especially the pay back period of 0.8 years , when is stage two planned to kick in ? and who prepared the PFS ?

    Item Measure PFS Life of mine years 8.5 Average annual production tpa 93,000
    Plant feed rate tpa 883,000 Average head grade % TGC 10.6%
    Average annual EBITDA US$m 112 Basket sales price FOB Mtwara
    US$/t 1,777 Operating cost per tonne of product US$/t 500
    Operating margin US$/t 1,277
    Stage 1 capital cost US$m 43.6
    Stage 2 capital cost US$m 32.5
    Post-tax NPV (10% discount rate) US$m 349
    Post-tax internal rate of return (IRR) % 131 Post-tax payback period Yrs 0.8
 