    osiel oil flowing KALREZ ENERGY LIMITED 2003-02-06 ASX-SIGNAL-G

    HOMEX - Perth

    +++++++++++++++++++++++++
    Kalrez Energy Limited is a 2.5% shareholder in the Seram Joint
    Venture that operates the Oseil oilfield. The major shareholder, and
    Operator of the JV, is KUFPEC (Indonesia) Limited with 97.5%.

    Production from the Oseil oilfield commenced on December 30th 2002,
    with processing taking place through a Temporary Production System
    ("TPS") nominally rated to approximately 12,000 barrels per day
    throughput.

    The TPS facility is a temporary process facility to be utilized until
    the permanent facilities currently being installed are completed.
    Current expectations are that the permanent facilities will be
    available during April 2003.

    REPORTING PERIOD From midnight To midnight
    26/01/2003 02/02/2003

    Oil produced for the period 50,592 barrels of oil
    Average daily production for
    the period 7,227 barrels of oil
    Cumulative Oil produced 250,316 barrels of oil
    Oil sold during the period 0 barrels of oil
    Oil in stock 250,316 barrels of oil

    The above represent total production from the Oseil oilfeld as
    reported by the Operator. Kalrez entitlement is 2.5% of this
    production after deducting operating costs and Indonesian government
    entitlements.

    COMMENTS

    All three wells, Oseil #1, Oseil #2 and Oseil #4 are on production.

    Steam heaters arrived on location 3rd February 2003 and are presently
    being connected into the TPS process system to assist in combating
    foam induced process problems and to aid water separation (emulsion
    breakdown).

    At 22:30 hours on 2 nd February 2003 loading of the tanker Shanghai
    was completed and at 02:00 hours on the 3rd February 2003, the
    loading hose was disconnected and the vessel departed, signifying
    completion of the first consignment of crude oil from the Oseil
    oilfield. The consignment of 250,316 barrels represents 241,299
    barrels corrected to 60 degrees Fahrenheit.

    BEGINS SECOND LIFTING

    By 16:00 hours 3rd February 2003, the tanker Swallow was berthed and
    the loading hose connected ready for receiving crude oil.

    Current operations are that production has recommenced and the
    Swallow is being loaded with Oseil crude oil.

    For further information please contact:-

    Mr Russell Brimage Or Mr Giuseppe (Joe) Mercorella
    Jakarta Office Adelaide Office
    Ph: 0011 6221 7696977 Mobile: 0403680570
    Fax: 0011 6221 7697012 Ph: 08-82391344
    Email: [email protected] Fax: 08-82391744

    Mr Eddie Smith Email: [email protected]
    Perth Office
    Ph: 08-93629330
    Fax: 08-93629331

    A copy of the Background Information is available in PDF format on
    www.asx.com.au. Alternatively it is available for purchase from
    ASX Customer Service on 1 300 300 279.
 