SIH sihayo gold limited

Very good update, but as usual looks as the market will ignore...

  1. 20,457 Posts.
    lightbulb Created with Sketch. 269
    Very good update, but as usual looks as the market will ignore it:


    OPERATIONAL AND DFS UPDATE
    POTENTIAL 22% LIFT IN ANNUAL AVERAGE GOLD PRODUCTION
    & 10% REDUCTION IN AVERAGE SITE CASH OPERATING COSTS
    (INCL ROYALTIES


    The Board of Sihayo Gold Limited (ASX: SIH) is pleased to provide an Operational and Definitive
    Feasibility Study (?DFS?) update for its 75% owned Sihayo Pungkut Gold Project (?SPGP?) in North
    Sumatra, Indonesia.

    Operational Update

    Drilling activities at the SPGP are set to resume in late September, following the end of the
    Ramahdan period and the associated public holidays, with a focus on the final phase of infill drilling
    for the SPGP. An infill programme of approximately 3,000 meters is required to likely convert the
    limited amount of Inferred Resource contained within the overall JORC compliant resource into the
    higher Indicated category. The programme will be undertaken with two diamond drill rigs and given
    the relatively shallow depth of the planned holes it is anticipated that the drilling will be completed
    within three months.

    Once the infill programme is complete, ongoing exploration drilling shall target potential nearsurface
    mineralisation along strike from the existing JORC Resources, which could potentially be
    included in the early years of the current proposed mine schedule as described within the DFS.

    Figure 1 below shows the Sihayo and Sambung Resources and highlights the potential resource
    extensions to the northwest and southeast of the Sihayo deposit.

    Government and Community meetings

    As previously reported, on Sunday 29th May, a group of demonstrators, believed to be supported by
    the representatives of illegal artisanal miners from the region, arrived and caused significant damage
    to Sihayo?s exploration camp.
    Over the past three months, our company relations team has conducted over forty meetings with
    the key SPGP stakeholders including; local community members, village heads, religious groups,
    NGO?s, local and provincial Government representatives, local and provincial Police and Army
    commanders, the newly elected Bupati of Mandailing Natal, North Sumatra and the Governor of
    North Sumatra. The meetings have been focused on ensuring that the future activities of the
    Company are conducted in a safe and secure environment without the risk of any further unlawful
    acts against the Company.

    As with any mining project, our relationship with the local community is critical to our long term
    operational success. As part of our ongoing community programme we are taking 15 local
    representatives on a site visit to a newly commissioned gold mine in North Sulawesi, Indonesia in
    mid‐September, to show them first‐hand the operational, environmental and community aspects of
    a mine of similar size to our planned SPGP.

    Definitive Feasibility Study (?DFS?)


    The final phase of the DFS work related to the overall metallurgical gold recoveries is progressing
    well. Over 4,500 additional cyanide leach tests are being completed (1,500 completed to date)
    across the multiple mineralisation types that make up the Sihayo and Sambung Resources and the
    initial results suggest that some improvement in overall process gold recoveries maybe achievable.
    It is anticipated that the metallurgical work will be completed by the end of October.

    Ongoing assessment of the ?optimal plant capacity? has indicated that an increase from the current
    1.25 mtpa capacity to a rate of 1.5 mtpa is economically positive. The Capex and Opex components
    of an expansion to 1.5 mtpa have been completed to DFS standard and the key summary results are
    detailed in the table below. An additional scenario of improved recoveries over the initial mine life
    has also been included in the table, however, it needs to be emphasised that this is merely for
    indicative purposes at this stage and any improvement in overall recoveries will be confirmed at the
    conclusion of the current metallurgical testwork programme.

    The Sambung Resource has been included in the mining schedule of the expanded 1.5 mtpa
    throughput case, however, it must be noted that the

    Sambung Resource is currently in the Inferred
    category and therefore will require a successful infill drilling programme to bring the resource up to
    the required Indicated category for its ultimate inclusion in the DFS mining schedule.

    Key DFS parameters for the 1.25 mtpa and 1.5 mtpa cases
     1.5 mtpa case delivers 22% increase in average annual gold production and 10%
    decrease in site cash operating costs (including royalties) compared with 1.25 mtpa
    case

    Sihayo Pungkut Gold Project 1.25 Mtpa 1.5 Mtpa 1.5 Mtpa *
    Capital Cost (pre contingency allowance) USD mill 80.4 87.1 87.1
    Pre‐production mining USD mill Nil 11.2 11.2
    Initial Mine Life years 7 7 7
    LOM Total ore processed** Mt 8.6 10.2 10.2
    LOM Average anual gold production Oz 72,000 88,000 93,000
    LOM Site Cash Costs (including royalties) US$/oz 752 678 639
    LOM average gold recoveries % 71.5 71.5 75*
    LOM average strip ratio Waste:Ore 5.4:1 4:1 4:1


    Sambung JORC Resource

    Runge Limited completed an updated JORC Resource report for the Sambung Resource in July 2011.
    Whilst there has not been any additional drilling since the previous JORC Report completed in
    January 2007, Runge have used the greater knowledge base obtained during the preperation of the
    latest JORC Report for the Sihayo Resource to assist in the completion of the new Sambung Report.

    In summary, the new JORC report saw an increase in the estimated contained gold from 100,000oz
    to 123,200oz, a decline in the average grade from 2.6 g/t Au to 2.2 g/t Au and a revised cut‐off grade
    of 1.2 g/t compared to 1.5 g/t previously. The table below details the new Sambung JORC resource

    Sambung Inferred Mineral Resource Estimate
    Type Tonnes Au Au Au
    t g/t ounces cut‐off
    Oxide 313,000 2.3 22,900
    Transitional 1,404,000 2.2 100,100
    Fresh 4,000 2 200
    Total 1,721,000 2.2 123,200 1.2 g/t

    Regional Exploration

    For the entire period of the disruption at our main project, regional exploration work at Tambang
    Tinggi, Hutabargot Julu and Huta Pungkut, including drilling at Tambang Tinggi, has continued
    without issue. Refer to Figure 2 below for the location of all prospects.

    Hutabargot Julu epithermal gold prospect

    The work program has significantly expanded the known mineralisation potential of the prospect to
    the north, east and west. The underlying geology, soil and rock chip geochemistry results are
    contained in Figures 3 ? 5 below.

    New mineralised vein systems have been discovered to the east (fault vein) and to the north
    (Kaporas prospect). Soil and IP programs will be extended to the northwest to cover the expanding
    anomalous zones.

    The Kaporas East soil gold anomaly is approximately 1 x 1 km sq and open under cover to the east.
    The anomaly is consistent with a broad area of magnetite destruction (alteration) and represents a
    high priority target for bulk tonnage gold potential.
    The Kaporas West soil gold anomaly is also approximately 1 x 1 km sq and is open to the north and
    the west and is consistent with a mapped granodiorite intrusive.

    Gold mineralisation at Hutabargot Julu is hosted in epithermal veins and structures within a northsouth
    trending belt of dacitic volcanics. The mineralised vein systems are covered to the south by
    post‐mineral acidic (dacite‐rhyolite) flows and pyroclastics and to the east by quaternary alluvium.

    Hutabargot Julu is a high priority for further exploration and potential discovery of both high
    grade ? low tonnage gold deposits and bulk tonnage ? low grade gold deposits and is located only
    8km along trend from the Sihayo and Sambung Resources.

    Drilling is expected to commence in late September.
    Tambang Tinggi gold and copper / gold
    Drilling of the multiple near surface gold targets in the Tambang Tinggi Region is nearing the
    completion of the first phase. The second phase of the drilling programme will be a series of deeper
    holes testing the copper / gold potential indicated by the results of holes TTDD011 and TTDD008.
    Conclusion

    With the final phase of infill drilling about to commence at our main project and concurrently a recommencement
    of drilling at the highly prospective Hutabargot Julu epithermal gold prospect, the
    next six months should prove to be a very exciting period for our Company.

    Yours faithfully,
    SIHAYO GOLD LIMITED
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.