SIH sihayo gold limited

operational and dfs update

  1. 20,457 Posts.
    lightbulb Created with Sketch. 269
    OPERATIONAL AND DFS UPDATE
    DRILLING RECOMMENCES AT SIHAYO-SAMBUNG
    COST OPTIMISATION PROGRAM ON TARGET TO DELIVER
    SUBSTANTIAL REDUCTIONS IN SITE CASH OPERATING COSTS

    The Board of Sihayo Gold Limited (ASX: SIH) is pleased to provide an Operational and Definitive
    Feasibility Study (“DFS”) update for its 75% owned Sihayo Pungkut Gold Project (“SPGP”) in North
    Sumatra, Indonesia.

    OPERATIONAL UPDATE

    Infill drilling program at Sihayo-Sambung
    Drilling activities at SPGP have resumed with a focus on the final phase of infill drilling. An infill
    program of approximately 3,000 meters is required to likely convert the limited amount of Inferred
    Resource contained within the overall JORC Compliant Resource of 16.3Mt at 2.7 g/t Au for 1.425
    Moz into the higher Indicated Category. The program has begun with a single rig and a second rig
    shall arrive on site within 4 weeks. With two diamond drill rigs and the relatively shallow depth of
    the planned holes it is anticipated that the drilling will be completed within two or three months.
    Once the infill program is complete, ongoing exploration drilling shall target potential near-surface
    mineralisation along strike from the existing JORC Resources, which could potentially be included in
    the early years of the current proposed mine schedule as described within the DFS.
    Figure 1 shows the Sihayo and Sambung Resources and highlights the potential resource extensions
    to the northwest and southeast of the Sihayo Deposit and the infill drilling program.

    Exploration drilling at Hutabargot Julu

    Drilling has recently commenced at the highly prospective Hutabargot Julu Epithermal Gold Prospect
    located 7km southeast, along strike, of the SPGP. Figure 2 shows the location of the SPGP and
    Hutabargot Julu Prospect with the wider Contract of Work (“COW”) area.
    Ongoing exploration at Hutabargot Julu has defined an intermediate sulphidation epithermal gold
    complex that has a footprint of approximately 6km * 2km. Historic drilling yielded a best intercept
    of 5m @ 36.7 g/t Au and 198 g/t Ag from 47m within Quartz-Sulphide veining. The current drilling
    program will test multiple Epithermal Veins (high grade gold / moderate tonnage potential) and
    Hydrothermal Breccias (lower grade gold / high tonnage potential) and will consist of an initial
    10,000m of drilling. Figure 3 is a surface plan of Hutabargot Julu summarising exploration work to
    date, current drilling status and planned ongoing drilling.

    "It is exciting to be drilling the highly prospective Hutabargot Julu Gold Prospect concurrent with
    completing the last phase of infill drilling at our flagship Sihayo Pungkut Gold Project. The
    prospect is located 7km southeast of Sihayo Pungkut and has the potential to provide significant
    upside to our overall resource inventory” said Paul Willis, Chief Executive Officer.
    Community, Government and other Stakeholder Meetings
    As previously reported, on Sunday 29th May, a group of demonstrators, believed to be supported by
    the representatives of illegal artisanal miners from the region, arrived and caused significant damage
    to Sihayo’s exploration camp.
    Over the past five months, our community relations team has conducted over sixty meetings with
    the key SPGP stakeholders including; local community members, village heads, religious groups,
    NGO’s, local and provincial Government representatives, local and provincial Police and Army
    commanders, the newly elected Bupati of Mandailing Natal, North Sumatra and the Governor of
    North Sumatra.
    The meetings have been focused on ensuring that the future activities of the Company are
    conducted in a safe and secure environment without the risk of further unlawful acts.
    As with any mining project, our relationship with the local community is critical to our long term
    operational success. As part of our ongoing community program we took 15 local representatives
    on a site visit to a newly commissioned gold mine in North Sulawesi, Indonesia in mid-September, to
    show them first-hand the operational, environmental and community aspects of a mine of similar
    size to our planned SPGP.
    In addition, community agriculture based programs have been initiated in four of the villages
    surrounding the SPGP and the aim is to establish similar programs in each of the 15 villages that are
    located in the project’s primary area of influence.
    The agriculture programmes work very well in these communities where over 90% of the local
    population are engaged in agriculture production as their primary source of income. The programs
    are built on the core philosophy of “sustainability” and seek to improve the overall productivity of
    the local producers, add value to their existing products and ultimately facilitate better marketing of
    their products.
    The response from within the initial four villages has been extremely encouraging and bodes well for
    the continued establishment of similar programs in the remaining 11 villages.

    DEFINITIVE FEASIBILITY STUDY (“DFS”)

    Metallurgical Testwork

    As previously reported, the final phase of the DFS work related to the overall metallurgical gold
    recoveries is progressing well. Over 4,500 additional cyanide leach tests are being completed (2,750
    completed to date) across the multiple mineralisation types that make up the Sihayo and Sambung
    Resources and the initial results suggest that some improvement in overall process gold recoveries is
    achievable.
    Optimal Plant Capacity
    Ongoing assessment of the “optimal plant capacity” has confirmed that the project will be a 1.5Mtpa
    operation.

    Cost Optimisation – Biomass Power

    Currently in the DFS, power production is based on diesel generators and at a basis of US$100/bbl
    oil, the unit cost of power is approximately US$0.25 kw/hr.
    Our study of hydro power potential was unsuccessful due to the high Capex associated with the
    required infrastructure.
    However, we have entered detailed discussions with a number of industry leading biomass power
    companies, including DP Cleantech, to determine the viability of an 8MW biomass power plant being
    the primary source of power.
    DP Cleantech have designed, constructed and successfully commissioned over 40 biomass power
    plants across Asia and Europe with a combined installed capacity of 1,000MW.
    The primary fuel source for the proposed power plant is Palm Kernel Shells (“PKS”) a waste product
    of the palm oil production process.
    The PKS market is well established in Sumatra, Indonesia and export volumes of PKS to North Asia
    and Europe as a primary fuel for biomass power plants has been steadily increasing over the past
    five years.
    Potential supply of PKS within trucking distance of the proposed power plant site exceeds 3 times
    the annual required supply and is available across multiple independent suppliers. In addition, new
    palm oil plantations are being established within the area and will provide additional future supply
    of PKS.
    From both an environmental and operating cost perspective, the potential to utilise proven biomass
    power supply is an attractive proposition.
    Biomass power would provide an approximate 70% operating cash cost saving compared to diesel
    generated power, excluding any carbon emission credits that maybe available.
    DP Cleantech will provide DFS Capex and Opex estimates for the biomass power plant by the end of
    December 2011.
    Cost Optimisation – Overland conveyor for waste material
    The current waste material movement process is via haul trucks. Given the topography surrounding
    the proposed pits and waste dump areas, the required haulage distance from pits to waste dumps is
    up to 8km in the early years of operation.
    We have entered detailed discussions with some of Europe’s leading manufacturers of conveyors for
    the mining industry, including Famur Group of Poland, for the installation of an overland conveyor to
    transport up to 8Mtpa of waste material from nearby the mining pits to the waste dump site.
    The proposed conveyor will be between 1.2km and 2.0km in length and because the entire length of
    the conveyor will be downhill, the conveyor will generate excess power equivalent to approximately
    10% of the total power requirement of the entire project.
    Famur Group will provide DFS Capex and Opex estimates for the overland conveyor by the end of
    December 2011.


    Conclusion

    With the final phase of the DFS progressing well and the potential significant cost savings within
    power production and waste material movement, the economics of the Sihayo Pungkut Gold Project
    are looking very attractive.
    Together with the DFS work, the final phase of infill drilling and concurrently the re-commencement
    of drilling at the highly prospective Hutabargot Julu Epithermal Gold Prospect suggests the next six
    months should prove to be a very exciting period for our Company.

    Yours faithfully,
    SIHAYO GOLD LIMITED
    Paul Willis
    Chief Executive Officer
    27th October 2011
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.