    Overall Delays between timeline provided in November vs latest timeline:

    • Start Delays: The cleanout and mitigation work initially planned for December 2024 and January 2025 has been delayed to February 2025.
    • Completion Delays: Flow testing has been pushed from January 2025 to March 2025.
    • Hosting Tier 1: Delay by 2 months
    • Extended Timeline: The overall timeline for mitigation, flow testing, and equipment removal has shifted by approximately 2 months.

    PHOENIX launched right issue in Sep 2024 and since then, no activity has been carried out.
 