"so much going on behind the scenes."
Like, there won't be any NCu sales at a premium? Rather, it will now be produced as DSO?
The three million tonne per annum off-take agreement with Sinosteel was a bit of a surprise too.
And I thought 85% of the plant was on site as of 9th August? Yet items in transit at 13th September still include:
High Pressure Grinding Rolls
Gravity Jig (alone costing over $20m)
Some structural steel
Small part of the NCu cleaning drum
Part of the Tower Mills
-