URL universal resources limited

positive feasibility study

  1. 20,457 Posts.
    lightbulb Created with Sketch. 269
    UNIVERSAL RESOURCES LIMITED
    ACN 090 468 018
    15 September 2006
    The Manager
    Company Announcements Office
    Australian Stock Exchange Limited (ASX)
    Electronic Transmission
    8 page(s)
    Dear Sir/Madam,
    UNIVERSAL ANNOUNCES POSITIVE FEASIBILITY STUDY FOR ROSEBY
    COPPER PROJECT
    Universal Resources Limited (Universal) directors are pleased to announce the results
    of the Feasibility Study on the Roseby Copper Project in the Mt Isa Region of North
    West Queensland.
    The study concluded that, based on the technical testwork and financial assumptions
    used, large scale development of the project is both technically and financially
    feasible.
    • Copper production targeted to commence in fourth quarter 2008 with overall
    timing determined by several long-lead items.
    • Roseby forecast to produce up to 34,000tpa of copper and 14,700oz of gold at
    competitive cash operating costs.
    • The project is viable at copper prices well below current copper price – payback
    period at US$2.00/lb is 3.6 years.
    • Project NPV increase to A$980.7M and IRR to 61.9% at US$3.50/lb copper
    price, demonstrating strong leverage to copper price upside.
    • Forecast capital expenditure of A$338 million includes significant contingency
    costs and A$48 million to acquire a mining fleet.
    • Cash operating costs consistent with rising costs across the industry
    • The current estimated life of the mine is 8.5 years.
    Under the development schedule outlined in the Feasibility Study, pre-stripping
    activities at Roseby will commence in late 2007 with ore treatment planned to
    commence in fourth quarter of 2008. The ramp-up to the planned rate of copper
    production of 34,400 tonnes per annum will occur relatively quickly, and is expected
    to be achieved within the first quarter of 2009. During the first three years of
    operations, there will also be an annual average of 14,700oz of gold production.
    HEAD OFFICE
    Level 2,
    91 Havelock Street, West Perth
    Western Australia 6005
    POSTAL ADDRESS
    P O Box 1466, West Perth
    Western Australia 6872
    Phone: +61 (0)8 9486 8400
    Facsimile: +61 (0)8 9486 8700
    Email: [email protected]
    Website: www.universalresources.com.au
    2
    The study confirms that the project has significant leverage to upside in the copper
    price, as evidenced by the financial indicators for the project at a number of different
    copper prices. Using a flat copper price of US$2.00 per pound from the project startup,
    the net present value (NPV) at a discount rate of 8.5% is A$156.5 million with an
    internal rate of return of 19.5% and a payback period of 3.6 years. With copper at
    US$3.50 per pound, the NPV is A$980.7 million with an internal rate of return of
    61.9% and a payback period of 1.4 years. The relevance of the US$3.50 per pound
    comparison is best illustrated when it is considered that the LME average cash price
    for copper during August was US$3.49 per pound.
    The physical and financial results of the study are tabulated below:
    Ore treatment rate tpa 5,000,000 to 8,000,000
    Payable copper produced per annum t 34,400
    Treatment Plant Capital Cost A$’000 248,443
    Mobile Fleet Capital Costs A$’000 47,970
    Pre Strip Cost A$M 41,370
    Total Capital Cost A$M 337,783
    USD/AUD Exchange Rate 0.72
    Copper Price US$/lb 2.00 3.50
    Operating Cost US$/lb 1.14 1.19
    Net Present Value @ 8.5% Discount Rate A$’000 156,500 980,700
    Internal Rate of Return % 19.5 61.9
    Payback in years 3.6 1.4
    The Feasibility Study evaluated an open pit mining operation and a processing plant
    capable of throughputs of up to 8 Mtpa on a blend of sulphide and oxide ore but with
    sufficient versatility to allow either sulphide or oxide ore to be treated separately.
    When treating sulphide ore alone the plant capacity is 5Mtpa. The plant comprises a
    crushing and grinding circuit, a rougher flotation, regrind mill and cleaner flotation
    circuit. In addition to the plant construction, the capital cost includes provision for on
    site accommodation, EPCM costs, tailings dam, pit dewatering, offices and all
    contingencies. Power will be supplied by a gas fired power station at Mt. Isa and
    reticulated to site by a dedicated transmission line.
    Mining will initially focus on three deposits: Little Eva, Blackard and Scanlon. These
    will supply feed to the treatment plant for a minimum period of 8.5 years. Initially the
    Little Eva deposit will be mined to provide higher grade sulphide ore feedstock. This
    sulphide ore is characterised by a high metallurgical recovery and the net effect of this
    treatment strategy is to maximise the cash flow in the early years of the project. All
    mill feed from these three deposits falls into the Proved and Probable Ore Reserve
    category except for a small proportion which comprises Inferred Resource captured
    within the pit design envelope. Drilling is currently in progress with the objective of
    converting this Inferred Resource to the Measured and Indicated Resource categories.
    3
    For the purpose of the study a non reserve mill feed tail has been included utilizing
    four of the nine other deposits identified at Roseby. These are two oxide deposits
    (Longamundi and Legend) and two sulphide deposits (Bedford and Lady Clayre).
    These four deposits are assumed to provide mill feed for the second half of 2016
    through to 2017.
    Mining
    It was initially assumed that contract mining would be undertaken at Roseby, however
    the Feasibility Study has demonstrated that there are considerable financial benefits to
    be derived from purchasing and operating the mobile equipment fleet. The fleet will
    comprise up to two 180-tonne class excavators, one 125-tonne class excavator and up
    to 10 150-tonne capacity dump trucks as well as a number of items of ancillary
    equipment. The mine will have a very low strip ratio averaging 2.6:1 across all of the
    deposits. The equipment will be used to mine at a rate of up to 28Mtpa in the first year
    of mining although this will decline slightly as the open pits become deeper. The
    Little Eva deposit will require a pre-strip of 20 million tonnes of waste prior to the
    commencement of ore mining operations.
    Metallurgy
    Pilot scale metallurgical test work has confirmed the native copper and sulphide
    copper can be successfully recovered separately or as a blended feed through the same
    treatment circuit. The optimum strategy which provides the highest net present value
    is to initially treat 5,000,000tpa of sulphide ore from Little Eva in the early years and
    later 8,000,000tpa of mainly oxide ore from Blackard and Scanlon combined with a
    small proportion of sulphide ore primarily from Little Eva. The recovery of copper to
    concentrate will be 95% in the sulphides and 63% in the native copper and oxide ore.
    This is in line with expectations from earlier studies. The average grade of the
    concentrate produced will be 34% copper although the sulphide and oxides will
    produce different grades of concentrate of 30% and 38% respectively.
    Capital Costs
    There have been cost increases across the mining industry and these have impacted on
    the capital and operating cost of the Roseby Project. However the project is highly
    leveraged to the copper price and, at copper prices above US$2.00/lb, the impact of
    cost increases has a diminished impact on the project economics.
    4
    The table below shows the main elements of the capital cost estimate used in the
    Feasibility Study.
    Item Cost A$
    Process Plant 138,199,000
    On site Infrastructure 37,490,000
    Owners Costs 15,770,000
    Contingency 22,748,000
    EPCM 34,236,000
    Sub Total Plant 248,443,000
    Mobile Equipment Fleet 47,970,000
    Pre strip 41,370,000
    Total 337,783,000
    There have been some cost increases associated with extra equipment requirements
    identified by the detailed pilot and bench scale test work as well as increases in the
    cost of most of the inputs to the project. The Feasibility Study has gone into far
    greater detail than the original study, both in the design work and the cost estimation.
    Direct comparisons between the two are only possible at a high level and detailed
    variance analysis is not meaningful because of this.
    Operating Costs
    Operating costs have been impacted by the increases in input costs for diesel fuel,
    labour, explosives, reagents and transport costs. There are a number of areas where
    costs have decreased and these have served to mitigate to some extent the overall cost
    per tonne of ore for the project. It is now planned to have a utility company build and
    operate a gas fired power station in Mount Isa and construct a transmission line to
    Roseby. The power cost incurred in this arrangement will be extremely favourable.
    The on site operating cost including mining, processing and administration averages
    A$15.01/tonne over the mine life while off site charges including transport, royalties,
    smelting and refining costs, price participation and transport participation charges
    average A$4.88/tonne to give a total operating cost of A$19.90/tonne of ore.
    Royalties
    All royalties associated with the project have been included in the study. These
    include State government royalties on gold and copper as well as a vendor royalty
    payable to Zinifex and Lake Gold of 1.5% of Net Smelter Return.
    Project Schedule
    A number of long-lead items of equipment will determine the start date for the
    project. These include the SAG mill which will take up to 98 weeks to design,
    manufacture and install and this will be the critical item in the project schedule. The
    anticipated start date for the project is now estimated to be in the fourth quarter 2008.
    5
    Ore Reserves and Mineral Resources
    The total Mineral Resources for the Roseby deposit at June 30th 2006 are summarised
    in the following table. These Mineral Resources are inclusive of the Ore Reserves.
    Deposit Resource
    Category
    Ore
    ‘000s
    Tonnes
    %Cu Contained
    Cu Tonnes
    g/t Au Contained
    Oz Au
    Little Eva** Measured 2,280 1.26 28,728 0.14 10,262
    Indicated 17,990 0.77 138,523 0.13 75,191
    Inferred 9,540 0.75 71,550 0.15 46,008
    Sub total 29,810 0.80 238,801 0.14 131,461
    Blackard** Measured 20,900 0.66 137,980 0.00 0
    Indicated 19,000 0.64 121,760 0.00 0
    Inferred 3,800 0.59 22,537 0.00 0
    Sub total 43,700 0.65 282,277 0.00 0
    Scanlan** Measured 0 0.00 0 0.00 0
    Indicated 15,400 0.65 100,010 0.00 0
    Inferred 4,300 0.79 34,129 0.00 0
    Sub total 19,700 0.68 134,139 0.00 0
    Bedford
    South**
    Inferred 710 1.25 8,875 0.32 7,304
    Bedford North* Inferred 1800 1.07 19,260 0.26 15,047
    Sub total 2,510 1.12 28,135 0.28 22,351
    Legend** Indicated 6,200 0.59 36,580 0.00 0
    Longamundi* Indicated 5,060 0.81 40,986 0.00 0
    Great Southern* Indicated 3,720 0.78 21,216 0.00 0
    Caroline* Inferred 4,000 0.80 32,000 0.00 0
    Lady Clayre* Inferred 4,500 1.12 50,580 0.19 74,654
    Total Measured 23,180 0.72 166,900 0.01 10,262
    Indicated 67,370 0.69 464,800 0.03 75,191
    Inferred 32,650 0.82 267,700 0.13 143,013
    Sub total 123,200 0.73 899,400 0.06 228,466
    * These resources were defined at a cut off grade of 0.5% copper for all material types.
    ** These resources were defined at a cut off grade of 0.3% copper for all material types
    Cu = Copper, Au = gold
    6
    The Ore Reserve for the Roseby deposits is summarised in the following table.
    Deposit Ore
    Type
    Reserve
    Classification
    Ore
    ‘000
    Tonnes
    %Cu Contained
    Cu Tonnes
    g/t
    Au
    Contained
    Au oz
    Little
    Eva
    Sulphide Proved 1,986 1.20 23,832 0.14 8,940
    Sulphide Probable 14,968 0.73 109,266 0.12 57,750
    Sub
    Total
    Proved &
    Probable
    16,954 0.78 133,098 0.12 66,690
    Blackard Oxide Proved 12,978 0.67 86,952 0.00 0
    Oxide Probable 3,432 0.68 23,338 0.00 0
    Sulphide Proved 461 0.75 3,457 0.00 0
    Sulphide Probable 338 0.65 2,197 0.00 0
    Sub
    total
    Proved &
    Probable
    17,209 0.67 115,944 0.00 0
    Scanlon Oxide Proved 0 0.00 0 0.00 0
    Oxide Probable 8,806 0.72 63,403 0.00 0
    Sulphide Proved 0 0.00 0 0.00 0
    Sulphide Probable 44 0.69 304 0.00 0
    Sub
    total
    Proved &
    Probable
    8,850 0.72 63,707 0.00 0
    Sub
    Total
    Oxide Proved &
    Probable
    25,216 0.69 173,693 0.00 0
    Sulphide Proved &
    Probable
    17,797 0.78 139,056 0.11 66,690
    Total Proved &
    Probable
    43,013 0.73 312,749 0.05 66,690
    In addition to the Ore Reserve contained within the pit designs there is also a quantity
    of Inferred Resource which cannot be classified as ore reserve under the JORC code.
    The following table quantifies this Inferred Resource contained within the pit designs.
    This has been included in the production schedules and cash flow calculations
    primarily in order to obtain the best representation of the ore body for equipment
    selection and costing purposes. Drilling is in progress to convert these Mineral
    Resources into Ore Reserves.
    The mine life on the basis of Ore Reserves is estimated to be 7.5 years and when the
    Mineral Resource tail is included this extends to 8.5 years.
    7
    Deposit Ore Type Inferred
    Resource
    Within Pits
    ‘000s
    Tonnes
    %Cu Contained
    Cu Tonnes
    Au
    g/t
    Contained
    Au Oz
    Little Eva Oxide
    Sulphide 1,466 0.72 10,578 0.12 5,656
    Blackard Oxide 0 0.00 0 0.00 0
    Sulphide 438 0.76 3,309 0.00 0
    Scanlon Oxide 1,135 0.58 6,645 0.00 0
    Sulphide 2 0.47 8 0.00 0
    Sub Total 3,041 0.67 20,540 0.06 5,656
    Bedford Oxide 0 0.00 0 0.00 0
    Sulphide 900 1.05 9,450 0.27 7,813
    Lady Clayre Oxide 0 0.00 0 0.00 0
    Sulphide 500 0.93 4,650 0.59 9,485
    Longamundi Oxide 2,138 0.65 13,897 0.00 0
    Sulphide 550 0.77 4,235 0.00 0
    Legend Oxide 4,000 0.60 24,000 0.00 0
    Sulphide 100 0.54 540 0.00 0
    Sub Total 8,188 0.69 56772 0.06 17,298
    Total 11,229 0.69 77,312 0.06 22,954
    Project Financing
    Universal has appointed Perth based Prime Corporate Finance to advise the company
    on the raising of debt finance for the project. BBY is advising the company on the
    provision of equity finance.
    Discussions are continuing with a number of banks with regard to financing the
    project and senior representatives from these banks have already made a site visit to
    conduct a preliminary field assessment. Snowden Associates Pty Ltd has been
    appointed to undertake a due diligence review of the feasibility study for the banks
    and, once this is complete, a follow up field visit will be undertaken by the selected
    banks.
    8
    In addition to the discussions and activities regarding debt and equity financing of the
    project, discussions have been held with representatives of a number of non bank
    Australian and international institutions - all of which have approached Universal with
    a view to potentially providing financing for the Roseby Project.
    Michael Hulmes
    Managing Director
    Information in this report that relates to exploration and feasibility results has been compiled by
    Maurice Hoyle who is a Fellow of the Australasian Institute of Mining and Metallurgy and has
    sufficient experience which is relevant to the activity which he is reporting on as a Competent Person
    as defined in the 2004 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral
    Resources and Ore Reserves’. Mr Hoyle consents to the inclusion in the report of the matters based on
    the information compiled by him, in the form and context in which it appears
    Information in this report that relates to ore reserves results has been compiled by Quinton de Klerk
    who is a Member of the Australasian Institute of Mining and Metallurgy and has sufficient experience
    which is relevant to the activity which he is reporting on as a Competent Person as defined in the 2004
    Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
    Reserves’. Mr de Klerk consents to the inclusion in the report of the matters based on the information
    compiled by him, in the form and context in which it appears
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.