So they reached TD of 2030m on the 17th March (nearly a week 'eh), the timeline as I see with the operations would be somewhat like this:
1) Run casing till TD (1.5 days)
2) Pump cement (6-8 hrs)
3) Wait on cement (atleast 24 hrs)
4) Run CBL logs to check the cement bond (1 day)
5) Perform Casing & BOP integrity test (1 day)
6) If no dramas with the above, perforate casing.
Note that once Cased, the hole is safe, so the crew could have taken a well deserved easter break (not sure just my thoughts). Given that they are 8 hours behind OZ timewise, its still the 1.39 am (tue). My guess is sometime this week we should see an update from KEY.
Goodluck to all holders.
- Forums
- ASX - By Stock
- KEY
- possibility of 30cents today
possibility of 30cents today, page-2
-
- There are more pages in this discussion • 21 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add KEY (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.1¢ |
Change
0.000(0.00%) |
Mkt cap ! $2.263M |
Open | High | Low | Value | Volume |
0.1¢ | 0.1¢ | 0.1¢ | $9 | 9.02K |
Featured News
KEY (ASX) Chart |