    Thanks, Chair, I fully agree with you. From the interview I gather it will be (at least) 3 more months before the testwork is finished. How much longer it will take to complete the whole BFS I don't know. The pipeline sheet says October. I think we've learned our lesson. The company just doesn't adhere to deadlines. I do see further potential trouble down the road securing raw material for the smelter. The pipeline sheet says "Apr 11 - Jul 11" for commissioning. It would be a good place to start actually hitting targets.