progress report 3, page-4

  1. Ya
    6,809 Posts.
    lightbulb Created with Sketch. 3829
    Should b on target by early May by my estimates, Digz.

    Think we had that fluid-loss issue at P1 around 3600m mark, so they'd just want to navigate thro' this section carefully. KR1 is a deeper well compared to P1 & P2 & we are still a long way off from the 6" section (or the business end).

    Next up we have the 12.25" section to drill, after installation/pressure testing of the BOP & then the 8.5" section + 7" CSG (pressure testing).

    Here's a quick comparison:

    P1: 17.5"-2288m, set 13" CSG, drill 12.25" till 3898m

    P2: 17.5"-2422m, set 13" CSG, drill 12.25" till 4098m

    KR1: 17.5"-2663m, set 13" CSG, wait on cement, pressure test BOP's, Drill 12.25" thereafter.

    Hope they can provide an update on Brazil soon.

 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
$1.86
Change
0.015(0.82%)
Mkt cap ! $1.361B
Open High Low Value Volume
$1.86 $1.88 $1.85 $7.514M 4.036M

Buyers (Bids)

No. Vol. Price($)
2 9813 $1.84
 

Sellers (Offers)

Price($) Vol. No.
$1.87 34172 2
View Market Depth
Last trade - 16.10pm 14/07/2025 (20 minute delay) ?
KAR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.