Since the last report issued on 22 May the 12 1/4” hole section was directionally
drilled from 2,620 mRT to 2,793 mRT while building angle to approximately 35
degrees from vertical. Wireline logs were run and then the 9 5/8” casing was run to
2,788 mRT.
Planned Activities: Cement 9 5/8” casing. Test casing and BOPs then directionally drill the 8 1/2” hole
section to the top of the Abiod Formation at approximately 3,000 m RT. Run and
cement 7” liner and prepare to drill ahead.
I would say looking at probably next Wednesday before we are well into Aboid formation.
- Forums
- ASX - By Stock
- JKA
- progress report
progress report
-
- There are more pages in this discussion • 7 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add JKA (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
I88
INFINI RESOURCES LIMITED
Charles Armstrong, CEO
Charles Armstrong
CEO
SPONSORED BY The Market Online