Here's my estimate of the timetable (for Yalgoo Iron) from here....
Final Due diligence: May 9th to 18th
Binding offer/Contract signing/Announcement: May 27th
Shareholder/FIRB Approval: June 30
Definitive Engineering Study (12 months): June 30 2012
Bankable Feasibility Study/Financial Investment Decision (6months): Dec 2012
Construction and Commissioning (18-24 months): Dec 2014
FWL will need up to $15m for 18 months worth of studies prior to FID.
Funding by the Chinese of feasibility will give them the right (not the obligation) to JV at say 50:50.
FWL will then need to raise up to $500m in debt/equity to fund their 50% of construction cost, which might mean further capital raising (dilution) before construction commences.
Additional funding of up to $5m would be required for Western Haematite feasibility. If they can prove a viable resource, production could commence by July 2012.
- Forums
- ASX - By Stock
- LCG
- project timetable
project timetable
-
-
- There are more pages in this discussion • 24 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LCG (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
FHE
FRONTIER ENERGY LIMITED
Adam Kiley, CEO
Adam Kiley
CEO
SPONSORED BY The Market Online