No real delays
on the 17th of july they said
The total cost to complete the well program including production testing is estimated to be US$59.8 million, with a total duration of 135 days (which is in line with the expected cost reported by Jacka on July 8). The estimated cost to date is approximately US$47.2 million and 110 days have passed since the rig arrived on location on 28 March.
so if you add 25 days(135-110) to 17th july you get
11 august
then today they said
Preparations are continuing for a production test of the Abiod Formation fractured limestone reservoir. The current forecast is that the test will commence in the week beginning 5 August and may take 4-8 days in total.
- Forums
- ASX - By Stock
- JKA
- psi81 ... test delay ... whats the problem ?
psi81 ... test delay ... whats the problem ?, page-2
-
- There are more pages in this discussion • 6 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add JKA (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
I88
INFINI RESOURCES LIMITED
Charles Armstrong, CEO & MD
Charles Armstrong
CEO & MD
Previous Video
Next Video
SPONSORED BY The Market Online