No real delayson the 17th of july they saidThe total cost to...

  1. 1,400 Posts.
    lightbulb Created with Sketch. 32
    No real delays

    on the 17th of july they said

    The total cost to complete the well program including production testing is estimated to be US$59.8 million, with a total duration of 135 days (which is in line with the expected cost reported by Jacka on July 8). The estimated cost to date is approximately US$47.2 million and 110 days have passed since the rig arrived on location on 28 March.

    so if you add 25 days(135-110) to 17th july you get
    11 august

    then today they said
    Preparations are continuing for a production test of the Abiod Formation fractured limestone reservoir. The current forecast is that the test will commence in the week beginning 5 August and may take 4-8 days in total.
 