Last week I had posted a table suggesting cash costs of around...

  1. 1,166 Posts.
    lightbulb Created with Sketch. 7
    Last week I had posted a table suggesting cash costs of around US$1160. Whilst the cash costs of US$1150/oz are still high, I see some improvements in cash costs / tonne movement. Portends to improving performance in the next few qtrs.

    Column 1 Column 2 Column 3 Column 4 Column 5 Column 6
    0 September -Qtr Actual September -Qtr Proforma June -Qtr March-qtr
    1 Waste movement (t) 3,003,215 2,412,399 1,951,299 2,245,137
    2 Gold ore mined 415,017 341,567 284,771 308,681
    3 Strip ratio (waste/ore) 7.2 7.1 6.9 7.3
    4 Ore milled represents 4.6Mtpa 1,125,304 1,150,000 958,778 1,018,840
    5 Mined ore as % ore processed 37% 30% 30% 30%
    6 Head grade 1.04 1.10 1.04 1.10
    7 Recovery 90% 90% 88% 90%
    8 Gold recovered 33,864 36,604 28,211 32,429
    9 Gold sold as per announcement 41,657 41,468 30,483 38,757
    10 Adj production 41,657 41,468 30,483 38,757
    11  
    12 On-site production costs assuming $15.4/t material moved 36.5 42.3 30.9 22.3
    13 On-site admin costs 2.9   2.2 2.2
    14 Royalties 1.1 0.7 0.7 0.7
    15 Credits -0.7 -0.9 -0.9 -0.3
    16 Total cash costs 39.8 42.2 32.9 24.8
    17 Cash costs (US$/oz)  
    18  
    19 Per ozs basis  
    20 On-site production costs 877 1,018 1,013 576
    21 On-site admin costs 70   72 57
    22 Royalties 26 17 23 17
    23 Credits -17 -21 -28 -9
    24 Total cash costs 956 1,014 1,080 641
    25  
    26 (in US$M)  
    27 On-site corporate costs 1.4 0.8 0.8 0.7
    28 Exploration costs Higher exploration during Qtr 1.2 5.0 0.7 1.8
    29 Capitalised stripping 4.2   1.3 5.5
    30 Capex 1.3 0.5 0.5 0.8
    31 8.1 6.3 3.4 8.8
    32 Per ozs basis  
    33 On-site corporate costs 33 19 26 18
    34 Exploration costs 29 121 24 47
    35 Capitalised stripping 101   43 142
    36 Capex 31 12 17 21
    37 194 152 110 228
    38  
    39 Total AISC 1,150 1,166 1,190 869
    40 $/material mined (on-site costs + capitalised stripping)/material moved 12.8 15.4 15.4 11.8
    41 $/milled ore 35.1 36.8 34.5 24.1