So much for that turkey who keeps telling us that the gold project is behind schedule...note plant commissioning still projected for end 2002!!!
OXR - ASX Company Announcement $gen0 THIS IS A PRIORITY ITEM 28 October 2002 Part 1/2 -------- OXIANA RESOURCES NL -------------------
HOMEX - Melbourne ------------------------- Third Quarter Activities Report
QUARTERLY REPORT SEPTEMBER 2002
HIGHLIGHTS
SEPON PROJECT 80% OXIANA, 20% RIO TINTO
GOLD
Construction is on schedule for plant commissioning end 2002. In-fill and extension drilling at Discovery West, the first deposit to be mined, has outlined high grade extensions.
Scout drilling at the nearby Luang Prospect has intersected significant near surface gold mineralisation.
COPPER
The Bankable Feasibility Study (BFS) was completed and preliminary results announced demonstrating world class project characteristics. The Khanong copper orebody is high grade, leachable, low cost and long life with outstanding economics and strong upside. Financing and more detailed engineering is now underway targetting plant commissioning end 2004 and first production early 2005.
Scout drilling at the nearby Thengkham copper prospect intersected high grade copper mineralization over 3 kilometres of strike. The potential for a supergene deposit with similar characteristics to Khanong is considered high.
CORPORATE
Oxiana listed options were 99% exercised by optionholders by the expiry date of 30 September 2002, leaving 1% for the underwriters. This added $59m to the treasury and completes the Sepon Gold Project financing. Oxiana remains debt and hedging free.