ghost1, you can start by getting posters names right, just common courtesy. however i can continue to post to you in the manner you deserve if you wish.
you point out that it took canmex 7 weeks to get regulatory approval. Do you believe that this is the fault of canmex, have you stopped to think, or ring, the reason for the regulatory approval and who needs to provide it. Where was the delay?
As for getting a rig in place, it is not unheard of for mid size oilers to have a 12-18 month wait for a rig to arrive. However, the operators of canmex have extensive infrastructure and are well connected so a rig could theoretically be in place within 6 months. This all depends on the importance the operators place on this project.