Mine Pre-Production 1,005,000
Owner’s Pre-Production Capital 3,353,000
Mining Equipment 5,722,000
Mine Starter Tailings Dam 1,790,000
Ore Processing Facilities (Includes
Infrastructure) 10,236,000
Ancillaries 302,000
Indirect Costs 3,036,000
Purchase Interest in Gran Porvenir & La
Chayantena 500,000
Reclamation (End of Mine Life) 400,000
Post Mine Closure Monitoring 100,000
Sustaining Capital Mining Equipment &
Tailings Dam Lifts 6,594,000
Total Project Capital Cost $33,038,000
Working Capital $1,611,000
Working Capital Recaptured in Year 10 -$1,611,000
- Forums
- ASX - By Stock
- BIG
- rau need 33m in capital to start the project
rau need 33m in capital to start the project
-
- There are more pages in this discussion • 2 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add BIG (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
LU7
LITHIUM UNIVERSE LIMITED
Alex Hanly, CEO
Alex Hanly
CEO
SPONSORED BY The Market Online