rau need 33m in capital to start the project

  1. cya
    3,836 Posts.
    Mine Pre-Production 1,005,000
    Owner’s Pre-Production Capital 3,353,000
    Mining Equipment 5,722,000
    Mine Starter Tailings Dam 1,790,000
    Ore Processing Facilities (Includes
    Infrastructure) 10,236,000
    Ancillaries 302,000
    Indirect Costs 3,036,000
    Purchase Interest in Gran Porvenir & La
    Chayantena 500,000
    Reclamation (End of Mine Life) 400,000
    Post Mine Closure Monitoring 100,000
    Sustaining Capital Mining Equipment &
    Tailings Dam Lifts 6,594,000
    Total Project Capital Cost $33,038,000
    Working Capital $1,611,000
    Working Capital Recaptured in Year 10 -$1,611,000
 