re:drilling report, page-9

  1. 1,882 Posts.
    re: drilling report Updated 23 Nov

    Highlights
    POE 7 Sealed no flow rates identified.

    ...............Drilling ...F........G......H Stone

    POE 1..........O .....................(dificulty, rig to return later)
    POE 2 .........X ........P ......40 .....? + possible A sandstone
    POE 3 .........X ........P .......P .....25
    POE 5 .........X ........P .......P ......T
    POE 6 .........X ........T ......45......? 2 poss.extraspay zones above
    POE7 ..........X ........0 .......0.......0 Drill complete Zero pay
    POE8 ..........X........ P .......P ......P A-H zones should be tested
    POE 9 .........W .......? .......?.......? Pad under construction drill early Dec.

    Production .............0 .......85 ....25 .........= Total 110 bpd (+current non phase 1 production)

    100 barrels @ 20USD profit = CVN share of 40% $292KUSD per annum clear for CVN

    P = Perferation pending awaiting flow testing
    T = Flow rate testing in progress
    O = Drill rig operating
    W = Work not yet commenced
    X= Drilling complete
    ?= Not mentioned in releases.


    Phase 2 has 22 more wells to evaluate when completetd.

 