Hi BergerManHow do you want to define completion date?My...

  1. 1,912 Posts.
    Hi BergerMan

    How do you want to define completion date?

    My understanding of the steps are:

    Final drilling to target depth
    Running 7 inch perforated liner
    Well logging (may be before liner?)
    Short flow and Injection test
    Rig released
    1 month temp normalisation
    Longer flow and injection tests
 