Hi BergerMan
How do you want to define completion date?
My understanding of the steps are:
Final drilling to target depth
Running 7 inch perforated liner
Well logging (may be before liner?)
Short flow and Injection test
Rig released
1 month temp normalisation
Longer flow and injection tests