    For all those people, unfamiliar with infrastructure in/near Manono in the DRC.

    The Manono project is approximately 500km due north of Lubumbashi the capital of the Katanga Province in the South of DRC. The project area can be accessed from Lubumbashi by 1.5-hour flight or by road. There are roads there, but in poor condition. Mpiana Muanga Hydroelectric Power Station and transmission lines were damaged in 2007 by militant forces which require repairing. Dathomir Mining Resources SARL (10% owner of Manono project) will undertake repairs to this to facilitate the planed mine. Dathomir is co-ordinating the commitment of capital expenditure of up to USD $345 million for road upgrading from Lubumbashi to the project and refurbishment of the Piana Mwanga hydro facility. High quality road currently being built by China First Railway from Lubumbashi to Manono. Estimated to take 12 - 24 months to complete. The 1st 200km is already under construction.
    Contracts were awarded to the state-owned China Railway Construction Corporation Limited to rebuild the Luanda Railway and the Benguela Railway. A privately-owned Chinese mining company rebuilt the Moçâmedes Railway stretching 2,638 km in Angola the DRC’s neighbouring country. narrow gauge 1,067 mm (3 ft 6 in): The Benguela Railway connects to the Katanga Railway at the border with the Democratic Republic of the Congo.

    The maximum design speed is 90 km per hour.The design capacity is 20 million tons of cargo and 4 million passengers per year. There are 67 stations and 42 bridges along the route of the railway
    Passenger trains also ran between Lubumbashi and Lobito, connecting with passenger ship services to Europe. This provided a shorter route for Europeans working in the Katangan and Zambian Copperbelt, and the name "Benguela Railway" was sometimes used loosely to refer to the entire Lubumbashi–Lobito route, rather than the Luau–Lobito section to which it strictly applies.http://www.railwaygazette.com/news/...ents-inaugurate-rebuilt-benguela-railway.html

    China Railway Construction Corporation Limited(abbreviated CRCC) is a state-owned constructionenterprise based in Beijing China, that is the second largest construction and engineering company in the world by revenue in 2014. They loaned Angola $500 million USD interest free in 2006. See link http://china.aiddata.org/projects/39153?iframe=y
    http://www.chinadaily.com.cn/business/2017-03/26/content_28682186.htm
    And another link http://africachinareporting.co.za/2...the-scramble-to-access-the-regions-resources/

    The preferred route would be to the port of Dar Es Salaam in Tanzania as it is the shortest route to china and the 1st segment of this article is relevant to DRC’s AVZ https://www.reuters.com/article/us-...oan-for-tanzania-port-expansion-idUSKBN19N0NG
    And another link http://news.xinhuanet.com/english/2017-07/02/c_136411443.htm

    It is noted that outcrops and exposures in pits suggest that the two largest pegmatites are the Carriere de L’est Pegmatite and the Roche Dure Pegmatite. Each of these alone is evidently as large or larger (Figure 2) than the famous Greenbushes Pegmatite in Western Australia where current resources are stated as 120Mt of 2.4% Li20.

    Port of Lobito http://www.megaloglda.com/index.php/en/port-of-lobito
    China has built the largest port in Africa at Lobito
    AVZ general info http://www.4-traders.com/AVZ-MINERA...ition-of-interest-in-Manono-Project-23834432/
    Information formulated directly from company announcements and links provided.
    Aug 2017 AVZ Announcement
    Sept Quarterly report 2017

    Manono Project previously owned by Geomines SA (Belgium mining company); operated 6 open pit mines from 1910-1982 on the Manono Kitotolo pegmatites, producing 140,000 - 185,000 tons of tin concentrate (Zairetain 1981).
    The pegmatites located within the Manono Project extend for a strike length of at least 13km, however only a limited portion was tested by historical mining and exploration activities. According to publicly available records, the Manono pegmatites were mined for their tin content between 1919 and 1980, during which time approximately 185,000 tonnes of cassiterite concentrate was produced, at an average of 1,850gm of cassiterite concentrate per cubic metre (g/m3) or approximately 1,330g/m3 tin. The ore was sourced mainly from alluvial and weathered pegmatite, and the pits were completed to a depth of between 25 and 45 meters.

    The profit-based tax for instance is set at the preferential rate of 30% (as opposed to the 40% corporate tax rate) and is levied on the net profits from exploitation. Mining royalties are currently set at 2% for non-ferrous metals.
    Majority of mines located near Manono are focused on Tin with China
    Minmetals operating a copper mine within 200km.
    DRC Electrical Infrastructure
    Piana Mwanga Hydro - Piana Mwanga would comprise an installation of up to a 32MW power plant- rehabilitation and addition of one unit.#
    The project was last evaluated in about 1990.
    The project needs to be restudied and data brought up to date, before being included in a generation plan. Earliest on-power is estimated to be 2018.
    There is room for 4 gen sets for total production of 64MW. Dathomir and Cominiere have agreed that Dathomir will secure up to USD45M funding for the rehabilitation of the Piana Mwanga hydroelectric power station.
    Multiple Train Transportation Options Exist
    Road to Lubumbashi then three rail freight options:
    Lubumbashi and from there to Dar es Salaam the route that tin and cobalt exports presently utilize.
    Lubumbashi and from there to Durban, South Africa as the copper mines current utilize.
    Angola by the Katanga Railway and then via the new route Benguela railway from Lobito on the Atlantic.

    https://hotcopper.com.au/threads/po...mber-3.3735798/?post_id=27692355#.WfN5FtE_Wf0


    Another excellent post from @@orionwoo (thanks)

    Orionwoo's post:

    --------

    Personally I don't think it's fair to apply too heavily discount to DRC projects. First of all, global demand is way exceeding the Lithium supply outside of DRC. Next thing is, China's involvement in that region reduces lots of risk IMO.

    Plus, let's take a look of the new one belt one road map:



    The circled area should be DRC if I understand it correctly. See how close that is to the new maritme silk road. Chinese companies could easily take advantage of it & build onsite factories near the mine. This reflects what you said in the earlier posts re what you were told by industry advisers. Hence that's why Chinese value DRC projects differently with lots of Australian firms / professional individuals as they simply know that place so much better than anyone else in the world. Now put ourselves in their position, it would be a no brainer to spend some money to secure a world class future resource as early as possible. It's a national strategy thing IMO, simply too big to ignore.

    I certainly think 50c should be very doable in near term & $1 valuation isn't too insane as are simply too cheap at the moment comparing with peers.


    https://hotcopper.com.au/threads/ru...04088/page-2069?post_id=28214247#.WfO1HNE_Wf0

    There might be other posts re infrastructure as well.
    Luckily we have so many excellent contributors.
    Thanks
    Let's enjoy the ride. 50c should be minimum target, imo
  2. This thread is closed.

    You may not reply to this discussion at this time.

 
watchlist Created with Sketch. Add AVZ (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.