    @Beaner68 , ‘ 1200 to 1500 meters batches to lab for analysis.’ Well if there’s 4 rigs spinning on site....all 4 rigs aren’t going to be drilling the same hole. I asked the question regarding shift time. The response was that the diamond drill rigs will be operating 2 x 12 hour shifts and the multi purpose rig when operating on RC will operate one then change to two when drilling diamond core.

    Conservatively running figures such as 6m per hour on the NQ and the RC up at around 10m. Over 24 hours x 0.5 lost time factor for weather/ maintenance/resetting/ etc. let’s say that’s 1 rig knocking out a 300m hole in about 3 days. That’s a combined meterage of about 1200m over the 4 rigs once rig 1 completes a bore , so that’s where those 1200 to 1600 meters OR results after each hole come from ie - when one rig knocks out a 300/400 meter hole..collectively the 4 rigs will have knocked out a 1200-1600 meter batch ( 4 holes ) / after each hole
    Last edited by Obe wan: 21/12/17
  2. This thread is closed.

    You may not reply to this discussion at this time.

 
watchlist Created with Sketch. Add AVZ (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.