Given Friday's announcement, I have updated what I see as the key announcement schedule as follows:
1. Initial resource estimate for Tally Ho - before 18th April.
2. Merrill Crowe unit commissioned and operating - early May.
3. Crushing/screening circuit upgrade completed/commissioned - early June.
In previous posts I had listed the commencement of loading and irrigation of the new leach pads as a key announcement, however I understand MMN have decided to now load the existing leach pad up to a height of approx 14 to 15 metres (current height ~ 8 metres) before commencing to load the new pads. Some of the spent ore from the existing pad will be used to cover the new pads in order to protect the HDPE liner from mechanical damage.