bit of good information i found in the december 10th 2010 release that i didnt know about the rail capacity GBG/Karrara have.
copy and pasted from the release.
"Some of the key areas where infrastructure has been upgraded include: • An increase in the capacity of the high-voltage power line, from 132kv to 330kv, connecting Karara to the State grid at Eneabba. This is sufficient to accommodate an ultimate production capacity of more than 36Mtpa; • Improved rail haulage capacity of the 85km spur line connecting Karara to the existing rail line from Morawa-to-Geraldton, increasing the capacity of the spur line to +36Mtpa. This line is being built as a dual gauge to allow conversion from narrow to standard gauge in the future;"
so they can transport up to 36mtpa on the Rail. So at least they have future thought in mind and if MGI(in the future)share their berth/port access like someone mentioned somewhere on the forum yesterday then they could eventually haul in the $ with the High %FE