The time for testing is 95% determined by what the reservoir engineers want as the flow period is generally far far longer than the time to rig-up and do the wireline or coiled tubing runs.
First time around they said 1-2 days per zone, assuming now that they want 3-4 days per zone (just a guess) and that each CT run to move a sliding sleeve is 18 hours for any rigging up, pressure testing, running in, shifting sleeves and pullong out + rigging down...
So if they did all 4 zones again they would need 4 runs x 18 hours. One run to install and one to retrieve the ESP (which may take a bit longer bus say 18 hours for simplicity).
That gives 4-1/2 days for CT work. 3 days per zone gives 12 days of flow - and you're over the 2 week mark.
If they are happy with info gathered on zone #2 then that is still 5x18 + 3x72 = 306 (~13 days).
That said, I'm sure "material information" has been gathered over the last 2 weeks and NDO have an obligation to announce it...
p1000
- Forums
- ASX - By Stock
- NDO
- so, last chance to get in or get out??
NDO
nido education limited
Add to My Watchlist
0.00%
!
69.0¢

so, last chance to get in or get out??, page-5
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
69.0¢ |
Change
0.000(0.00%) |
Mkt cap ! $157.2M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 20000 | 70.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
73.5¢ | 11797 | 3 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 20000 | 0.705 |
1 | 3000 | 0.700 |
1 | 15000 | 0.695 |
1 | 5859 | 0.690 |
1 | 3286 | 0.680 |
Price($) | Vol. | No. |
---|---|---|
0.735 | 11797 | 3 |
0.740 | 17687 | 2 |
0.820 | 29695 | 2 |
0.825 | 39408 | 1 |
0.845 | 11706 | 1 |
Last trade - 10.18am 17/06/2025 (20 minute delay) ? |
Featured News
NDO (ASX) Chart |
Day chart unavailable
The Watchlist
RC1
REDCASTLE RESOURCES LIMITED
Ronald Miller, Non-Executive Director
Ronald Miller
Non-Executive Director
SPONSORED BY The Market Online