    The time for testing is 95% determined by what the reservoir engineers want as the flow period is generally far far longer than the time to rig-up and do the wireline or coiled tubing runs.

    First time around they said 1-2 days per zone, assuming now that they want 3-4 days per zone (just a guess) and that each CT run to move a sliding sleeve is 18 hours for any rigging up, pressure testing, running in, shifting sleeves and pullong out + rigging down...

    So if they did all 4 zones again they would need 4 runs x 18 hours. One run to install and one to retrieve the ESP (which may take a bit longer bus say 18 hours for simplicity).

    That gives 4-1/2 days for CT work. 3 days per zone gives 12 days of flow - and you're over the 2 week mark.

    If they are happy with info gathered on zone #2 then that is still 5x18 + 3x72 = 306 (~13 days).

    That said, I'm sure "material information" has been gathered over the last 2 weeks and NDO have an obligation to announce it...

    p1000
 
watchlist Created with Sketch. Add NDO (ASX) to my watchlist
(20min delay)
Last
85.0¢
Change
0.000(0.00%)
Mkt cap ! $193.8M
Open High Low Value Volume
85.0¢ 88.0¢ 85.0¢ $123.7K 145.0K

Buyers (Bids)

No. Vol. Price($)
4 212002 85.0¢
 

Sellers (Offers)

Price($) Vol. No.
88.0¢ 29650 1
View Market Depth
Last trade - 15.59pm 10/07/2024 (20 minute delay) ?
NDO (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.