The time for testing is 95% determined by what the reservoir engineers want as the flow period is generally far far longer than the time to rig-up and do the wireline or coiled tubing runs.
First time around they said 1-2 days per zone, assuming now that they want 3-4 days per zone (just a guess) and that each CT run to move a sliding sleeve is 18 hours for any rigging up, pressure testing, running in, shifting sleeves and pullong out + rigging down...
So if they did all 4 zones again they would need 4 runs x 18 hours. One run to install and one to retrieve the ESP (which may take a bit longer bus say 18 hours for simplicity).
That gives 4-1/2 days for CT work. 3 days per zone gives 12 days of flow - and you're over the 2 week mark.
If they are happy with info gathered on zone #2 then that is still 5x18 + 3x72 = 306 (~13 days).
That said, I'm sure "material information" has been gathered over the last 2 weeks and NDO have an obligation to announce it...
p1000
- Forums
- ASX - By Stock
- so, last chance to get in or get out??
The time for testing is 95% determined by what the reservoir...
-
- There are more pages in this discussion • 10 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add NDO (ASX) to my watchlist
|
|||||
Last
88.0¢ |
Change
0.000(0.00%) |
Mkt cap ! $200.7M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 25000 | 86.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
88.0¢ | 66599 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 25000 | 0.860 |
2 | 85739 | 0.850 |
1 | 4000 | 0.810 |
1 | 62111 | 0.805 |
1 | 40500 | 0.800 |
Price($) | Vol. | No. |
---|---|---|
0.880 | 66599 | 1 |
0.970 | 19999 | 2 |
1.050 | 115000 | 2 |
1.090 | 50989 | 2 |
1.100 | 100000 | 1 |
Last trade - 16.12pm 19/07/2024 (20 minute delay) ? |
Featured News
NDO (ASX) Chart |
Day chart unavailable