    Without hinderance they could complete construction from civils to commissioning within 6-8 months.

    Without hinderance meaning:
    1. No stay of construction granted to the intervenors;
    2. They commence construction late April early May, funding ready to go, long lead items onsite ready to install when required (key aspect) and weather kind to them.

    It really is a relatively simple plant to complete, however a lot of site run piping that can take time.

    Reports show long lead items well advanced, if not complete by now, so that is a positive.

    As I stated before though, with no schedule communicated to shareholders for construction it is but an educated guess. A detailed project schedule in MS Project or Primavera I would love to see, but I doubt they will make anything like that available.

    If a stay is awarded, then forget about 2014 production, would be mid (at best) to late 2015.
 
watchlist Created with Sketch. Add PEN (ASX) to my watchlist
(20min delay)
Last
8.2¢
Change
-0.002(2.38%)
Mkt cap ! $261.3M
Open High Low Value Volume
8.5¢ 8.6¢ 8.1¢ $536.5K 6.476M

Buyers (Bids)

No. Vol. Price($)
1 30000 8.2¢
 

Sellers (Offers)

Price($) Vol. No.
8.3¢ 25000 1
View Market Depth
Last trade - 16.10pm 13/09/2024 (20 minute delay) ?
PEN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.