URL universal resources limited

I have simply started, Andy, IOIOIO and others - please add to...

  1. RRM
    726 Posts.
    lightbulb Created with Sketch. 7
    I have simply started, Andy, IOIOIO and others - please add to this. Let's get this polished and up and running. I thin the URL lawyers would also be a good source to submitt our disgust to - here is for now


    Timing Issues
    “It is anticipated that the revised Feasibility Study will be
    completed by late October 2007. If the study confirms that
    the project is economically viable and all permitting is
    completed on schedule, the mine could be in production
    by the first quarter of calendar 2009”


    Xstrata Management Issues
    “Following the Cabbage Tree Creek drilling, a program
    of up to eight deep holes is planned, including up to
    six holes beneath the Blackard deposit and two beneath
    Scanlan”


    Follow up Issues
    Wonga and Clyde
    “Two prospects, Wonga and Clyde, have the potential to
    develop high-grade copper-gold (sulphide) resources for
    the Roseby Project. They warrant further exploration
    during the 2007-08 year”

    • An update on Wonga was made on the 28/2/08 – but very limited. Where is the update on Clyde.


    Cameron River Tenement
    “Mineralisation within the Cameron River tenement has
    features in common with the Rocklands-Las Minerale
    deposits of Cudeco Limited, located some 12km to
    the south. Further geophysical surveys and drilling are
    planned for the current year”

    Mary Kathleen
    “A heliborne regional sampling program is also planned,
    to fully evaluate the rugged country lying within the
    influence of the Burstall and Godkin granites.
    Surface exploration is actively progressing within the
    MKPA and drilling of several of the advanced anomalies is
    planned for December quarter 2007”

    • some reports on Mary Kathleen were made in the first quarterly report of 2008 but no mention of any helborne regional sampling.

    Bushy Park
    “Down-hole TEM surveys and further drilling are planned
    to test this high-grade mineralization”

    Partially done and reported in first quarterly report of 2008

    The Collector Project in New South Wales
    “…has beenfarmed-out to Tri Origin Minerals Limited, and Burra,
    also in NSW, is the subject of advanced joint venture
    Your directors have been in discussions with a number
    of potential candidates to join the Board. I expect to be
    able to make an announcement in this regard prior to the
    Annual General Meeting”


    Increases/(decreases) to Salaries

    2007
    P A J Ingram 233,350
    M W H Hoyle 188,681
    T Quaife 286,655


    2006
    P A J Ingram 254,045
    M W H Hoyle 317,647
    T Quaife 191,435


    Mr. Hoyle - Pursuant to an employment agreement dated 11 April 2006:
    Term – three years. April 2009 when this comes to an end.

    Mr. Ingram – Employment Agreement: 30 May 2006- Term three years


    1st Quarterly Report set this timetable
    Finalisation of the DFS economic analysis at the end of February 2008.
    • Ordering of long lead-time items Q1 2008.
    • Granting of site access Q2 2008.
    • Construction commences, subject to financing, by Q4 2008.
    • Commissioning Q3 2009.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.