Does this answer your question. Ex announcement 30/12.
The Company acquired the New Celebration gold process facility 3 years ago and the facility
was disassembled and stored on-site at Mt Monger. Integra has executed a Guaranteed
Maximum Price (GMP) refurbishment, construction and commissioning agreement for the gold
processing facility with GR Engineering Services. Refurbishment of key process facility
components (ball mill and crushers) is well underway and the Salt Creek process facility site
will be handed over to GR Engineering on January 4, 2010 for commencement of construction.
Project commissioning and first gold production is expected to be September 2010.
- Forums
- ASX - By Stock
- IGR
- street talk today afr
street talk today afr, page-8
-
- There are more pages in this discussion • 7 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
CC9
Chariot Corporation (ASX:CC9) refines Black Mountain strategy, launching Pilot Mine to seize U.S. lithium opportunity