Swedish wave farm set for hook-up

  1. 2,291 Posts.
    lightbulb Created with Sketch. 118
    http://renews.biz/86285/swedish-wave-farm-set-for-hook-up/

    "Sweden’s Seabased Industry has installed 36 wave energy converters at its project in Smogen.
    The array of 30kW devices totals more than 1MW.
    A spokesman said Seabased had been waiting for a suitable weather window since November to install the units.
    Seabased expects to connect the devices to the Swedish grid in the coming weeks.

    The wave energy park in north-west Sweden is a collaboration between Finnish utility Fortum and the Swedish Energy Agency. Seabased hold permits allowing the site to install up to 10MW of its point absorber wave energy converters.

    “This wave power park has been planned for many years and naturally it is very exciting to see it physically taking shape,”said Fortum chief technical officer Heli Antila.

    Meanwhile, Ireland's Simply Blue Energy plans to install around 200 Seabased generators totalling 10MW at Cornwall's Wave Hub facility in the UK by early 2017."

    Carnegie should only need to install 10x 1mw units to achieve 10MW.
    How long will it take to install 200.........................................? to get the equivalent of just over 1x 8MW wind turbine at current technology??


    It can't be worth it....
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.