MMN macmin silver ltd

the australian mining reviev special macmin

  1. 247 Posts.




    [u][b]32 The Australian Mining Review AUGUST 2008
    SPECIAL PROFILE Twin Hills Silver Mine[/b][/u]

    [url]http://www.macmin.com.au/media/2008/AustMiningReviewAug2008.pdf[/url]




    Silver mine moving to increase production
    MACMIN SILVER’s Twin Hills
    Silver Mine in Texas, Queensland,
    should start increasing production in
    September-October after new processing
    equipment is installed.

    Chairman and chief executive Bob
    McNeil said the upgrade of the crushing
    and screening equipment was initially
    due for completion at the end of
    March, but the tight market for
    such equipment has meant that it
    is only being installed now.

    “We should start to increase
    capacity from September-October
    … but until we get some feel on
    how it works we’re a bit reticent
    to actually predict how much at
    this stage,” he said.
    “It will certainly be a
    substantial increase on the
    present production.”

    The Macmin crushing circuit
    currently crushed more than
    20,000 tonnes per month to the
    required minus 4mm.
    “Planning is proceeding to
    move to extended crushing hours,
    probably two eight hour shifts,
    but is still restricted
    by difficulty in hiring
    suitable personnel,” Mr
    McNeil said.

    “Because of intense
    competition for trained
    operators in the mining
    industry at present, we
    cannot hire sufficient
    trained personnel and
    consequently we have
    had to train our own
    operators.

    “This is time
    consuming.”
    Texas, near the border
    of NSW, is about 3.5
    hours’ drive south west
    of Brisbane.
    The Twin Hills Silver
    mine is 10km east of the
    township of Texas and
    most of the 52 people on
    the payroll are locals, Mr
    McNeil said.

    [b]History[/b]

    Exploration on the Texas Silver Project
    began in 1994 by the company and its joint
    venture partner, Hunter Exploration.
    Significant silver mineralisation
    was delineated by 1998 and Macmin
    re-acquired Hunter’s interest.
    After further extensive drilling, the
    initial Twin Hills feasibility study was
    completed at the end of 2000.
    In March 2004, as the international
    price for silver started to increase,
    Macmin decided to commit to, and raise
    funds towards, developing the Twin Hills
    Silver Mine.

    Site clearing began in 2005, along with
    staff recruiting and training.
    The following year saw overburden
    removed, the crushing plant installed and
    the electrowinning plant constructed.
    Mining began early last year in
    conjunction with the commissioning of
    the processing circuit and production of
    the first silver powder.

    Fine-tuning of
    the crushing and
    electrowinning plants
    continued throughout last
    year.

    [b]Heap Leaching[/b]

    Twin Hills used a heap
    leaching process that was
    introduced to the industry
    in the 1970s as a means
    to drastically reduce gold
    recovery costs, Mr McNeil
    said.
    “It is also effective with silver in certain
    circumstances,” he said.
    “This process has literally made many
    mines by taking low grade resources and
    transforming them into a viable mine.
    “Heap leaching involves placing
    crushed or run of mine ore in a pile built
    upon an impervious liner.
    “Cyanide solution is distributed across
    the top of the pile and the solution
    percolates down through the pile and
    leaches out the silver/gold.”
    The silver/gold laden pregnant solution
    drains out from the bottom of the pile and
    is collected for recovery.

    “Heap leaching generally requires 60
    to 150 days for processing ore that could
    be leached in 24 hours in a conventional
    agitated leach process,” Mr McNeil said.
    “Recovery is typically about 70 per
    cent as compared with 90 per cent in an
    agitated leach plant.

    “Even with this lower recovery
    performance, the process has found
    wide favour, due to the vastly reduced
    processing costs compared with agitated
    leaching.”

    Mining at Twin Hills is carried out using
    hired equipment operated, supervised and
    directed by Macmin staff.
    “Mining of ore and waste is proceeding
    to plan and there are no problems in this
    department,” Mr McNeil said.


    [b]Crushing[/b]

    To recover 70 to 72 per cent of silver from
    the rock, the ore must be a certain size.
    This is achieved either by crushing or
    during blasting of the ore prior to mining,
    Mr McNeil explained.
    But the crushing circuit, as specified
    by the feasibility study and operated on a
    single-shift basis, could not achieve sufficient
    crushed material due to maintenance
    problems with the crushing circuit, the
    inability to hire sufficient trained operators
    to run more than a single day shift, and
    inadequate screens to remove the fine
    fraction early in the crushing process.
    The screens incorporated in the current
    circuit were inadequate to remove the fines
    at an early stage in crushing, which resulted
    in the circuit clogging up and maintenance
    problems, he said.

    If crushing could have been maintained
    on a 24-hour basis, this problem could have
    been partly offset.
    A further unanticipated problem was
    that the ore was harder and more abrasive
    than predicted.
    To solve the problems, Macmin is
    upgrading the crusher with additional
    screening, adding a second contract
    crusher the circuit, incorporating closer
    drill and blast patterns in the mine plan
    to produce as much minus 4mm product
    as possible without crushing, moving to
    two shifts, and having a contract crushing
    supervisor on site.

    “Our initial target is to place 60,000
    tonnes of minus 4mm material on heaps
    each month, moving to 100,000/120,000
    tonnes per month as ore grades decrease,”
    Mr McNeil said.
    “This latter target may require further
    crushing capacity.
    “The timing of achieving the initial
    objective of 60,000 tonnes a month onto
    the heaps is difficult to predict.”


    [b]Silver[/b]
    The silver is extracted from pregnant
    solutions using an electrowinning process
    and the plant, which contains 180 cells,
    runs on a 24-hour, seven-day-a-week
    schedule.
    Each cell in the plant has not produced
    at the rate specified by the manufacturer
    but, by experimentation, its capacity is
    gradually being increased, Mr McNeil
    said.
    “Problems have also arisen with the
    coatings on some anodes and these have
    now been replaced,” he said.
    As the plant was designed with at least
    50 per cent overcapacity, the reduced
    capacity of each individual cell is not
    expected to be a problem with production
    in the near term, but could restrict
    expansion.

    The leaching solutions from the heap
    carry 60 to 90g/t silver and the plant has
    been inefficient in extracting or reducing
    the silver in leach solutions below 40g/t
    silver.

    These barren solutions, which still
    contain 40g/t silver, are then recycled to
    the heap, with further dissolved silver
    rebuilding the solutions to 60 to 90g/t
    silver, Mr McNeil explained.
    “There is a concern that it is inefficient
    to recycle solutions with as much as 40g/t
    contained silver,” he said.

    Consequently, a Merrill Crowe (or zinc
    precipitation plant) has been installed to
    remove further silver.
    “The intent is that silver will be
    reduced to 40g/t by electrowinning, then
    pass through the Merrill Crow, which will
    reduce silver content to less than
    10g/t,” Mr McNeil said.

    “This barren solution will then
    be recirculated to the heaps.”
    Macmin is selling some of the
    silver powder produced “as is” for
    specific applications.
    “However, an unexpected side
    effect of the EMEW plant is that
    it also extracts some other metals
    and the silver powder produced to
    date contains contaminants which
    are unacceptable to some buyers,”
    he explained.

    “These are removed before
    smelting and this being done
    successfully in Melbourne.
    “The silver powder can then be
    smelted, refined and sold.”

    [u][b]OnTrax gives mine a boost[/b][/u]


    FOR TWO months, OnTrax Crushing and
    Screening has been providing booster
    plant support for Twin Hills Silver
    Mine’s crushing operations in an effort
    to capitalise on the current commodity
    price.

    The company said it was experienced in
    campaign crushing such as for Brisbane’s
    Gateway/Leighton joint venture and along
    the coast.
    Quarry campaign crushing for other
    companies included contracts with Boral
    and Hansons.
    These jobs involved making aggregate
    in order for the fixed plant to maintain
    production.
    [green][b]OnTrax said it looked forward to a
    continuing association with Twin Hills.[/b][/green]
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.