5 new underground stations9km twin rail tunnels2025 scheduled...

  1. 71,633 Posts.
    lightbulb Created with Sketch. 134
    5 new underground stations
    9km twin rail tunnels
    2025 scheduled open date
    5000 jobs during the construction phase
    $10.9bn initial project budget
    $14bn current project budget
    $1.7bn extra taxpayer costs
    $187.8bn forecast state debt in 2027-28
    BIG BUILD BLOWOUTS
    West Gate Tunnel
    Initial cost: $6.3 billion
    Revised cost: $10.2bn
    Blowout: $3.9bn
    Initial completion date: 2022
    Current completion date: 2025
    Metro Tunnel
    Initial cost: $10.9bn
    Revised cost: $14bn
    Blowout: $3.1bn
    Initial completion date: 2026
    Current completion date: 2025
    North East Link
    Initial cost: $16bn
    Revised cost: $26.1bn (Total budget TBC)
    Blowout: $10.1bn
    Initial completion date: 2028
    Current completion date: 2028

 