The feasibility study had a construction timeline of 6 and a half quarters.
- If Q1 year3 is Dec 2025 then Year1 Q3 is June 2024 and the beneficial operational date is very early 2026 (but some commissioning product would probably be produced in 2025 enabling 2025 production claims to be arguably correct).
- If Q1 year3 is Sep 2025 then Year1 Q3 is March 2024 which is looking doubtful as you note.
Unless there's a heap of announcements in the next few weeks or the construction timeline has been reduced from what was outlined in the scoping study, E25 aren't producing before Sep 2025.Announcements can go bang, bang, bang but at the moment the market is pricing as if HPMSM projected revenues aren't happening anytime soon.
In October 2023 E25 noted:
Back in April 2023 the feasibility study had the timeline below:![]()
- Forums
- ASX - By Stock
- The Dawn of EV
E25
element 25 limited
Add to My Watchlist
6.67%
!
24.0¢

The feasibility study had a construction timeline of 6 and a...
Featured News
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
|
|||||
Last
24.0¢ |
Change
0.015(6.67%) |
Mkt cap ! $54.86M |
Open | High | Low | Value | Volume |
23.5¢ | 24.0¢ | 23.0¢ | $106.8K | 454.0K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 10500 | 23.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
24.0¢ | 379568 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 10500 | 0.235 |
2 | 7850 | 0.230 |
3 | 8694 | 0.225 |
4 | 23028 | 0.220 |
1 | 15000 | 0.210 |
Price($) | Vol. | No. |
---|---|---|
0.240 | 379568 | 1 |
0.245 | 39548 | 2 |
0.250 | 60000 | 3 |
0.255 | 51122 | 3 |
0.260 | 2600 | 1 |
Last trade - 16.10pm 19/06/2025 (20 minute delay) ? |
Featured News
E25 (ASX) Chart |
The Watchlist
RML
RESOLUTION MINERALS LTD
Craig Lindsay, In-Country CEO
Craig Lindsay
In-Country CEO
SPONSORED BY The Market Online