So as @ May 21 first up FCOT was stated by Nigel as....... : January 2023 then - it shifted to........: Q1 2023 Now the latest tweet states..... : March 2023 (for SC6)
as that is a clear timeline slip (since May 2021), is the mine construction (proper - not just grading ROM pads) of August 2021 (next month) under pressure of slipping.
If it is, to be fair I'll use the same slip as FCOT - 2 months...
In order to make March 2023 SC6 production then the whole mine construction, commissioning, hitting initial nameplate output etc.....
This means all construction will have 16 months for completion.
Is that likely?
Is that realistically achievable?
Is maintaining the near impossible best governance by the BoD for the "worlds largest hard rock lithium deposit"?