Thought it may be useful to quantify what's coming up.
Monty Feasibility study is ongoing Sept/Oct - Metallurgy Drilling Oct to Dec 2011 - Analysis of Monty Metallurgy Drilling Post Dec 2011 - Processing Plant design Post Dec 2011 - Mine Planning and Pit Design Etc. 2H 2012 - Plant Construction Commences Mid 2013 - Production
Bogdan Oct - Local contractors are managing permits and other matters in order to begin the first exploration programme. Nov - Jan 2012 - 2500mtr drill campaign
Elsienora commencing "shortly" - Deep drilling campaign (duration 2 months) Late 2011/early 2012 - Results of analysis
Peelwood Environmental Impact Study completed by Dec 2011.
+ Acquisitions which could happen any time....
All info lifted from the qrtly..