It aint clockwork, but i suppose it aint indoors, we cant control the weather or how hard the ground is ---
WELL 6H
9th October
Spudded
7th Nov
Was getting ready to be fracced.
Basically a 2-3 week drill period in this one.
30th November
6H had been Fracced, 1800 bbls of the 12750 bbls of fracc fluid had been recovered under the wells own pressure, a pump was being used to recover the remainder; oil and gas had been flowing to the surface in advance of any hydrocarbon returns
Another 3 weeks to Fracc the well.
14th December
The well has been completed and is shut down while permanent production facilities are installed.
19TH DEC
well 6H is having permant production equipment installed after fraccing had finished and the initial flow rates were 379 barrels per day. The surface pumps were being installed that week and a gas pipeline agreement was being negotiated.
28th December
Permanent equipment is now installed. Waiting on gas pipeline construction.
Some posters were nearly expecting the gas line to go in
within a couple of days, a few posts later we had it up to a couple of weeks, plus holidays, then the bad weather and then--
BINGO -
24th of January.
Gas pipeline has been completed & this 300+ barrel and Gas rich baby goes into production this week.
Well 8A
23rd October
8A was spudded
30th October
Drilling completed to 9400ft. This one was drilled in a week.
It was a months later....
30th of November
8A was preparing to be fracced.
fracing took 2 weeks and then another 3 to completely unload going by their announcements----
12th December
Hydraulic fraccing had been completed and a service rig was due in within a few days to drill out the plugs separation each frac interval; then they would put the well into production to return the frac fluids and begin production testing, good production levels were antisipated and as good as the first well due to electrical log information and oil flowing to the surface during drilling phase
19th Dec
Well 8A has completed fraccing and is unloading 28 barrels of frac fluid per hour.
28th of December
Fraccing has been completed & oil has come to the surface during frac fluid recovery.
Must have been substantial delays with weather and new years cos------
24th December – still unloading Frac fluid, and oil has broken through at 109 bars per day(this well was showing up oil during the drilling stage as per 12th December
Well 9M.
It took over 2 weeks to drill this one-
10th of December
Spuded & by the 12th of december they were down 580 ft at which time they antisipated 8 days to gat to the targeted 9400 feet.
14th December
It was down 3300 feet
19th December
Well 9M - drilling was still being done, they were 8000 feet through to the targeted 9000 feet.
28th December.
Drilling to target depth of 9500 ft has been completed. Preparing to frac during the second week of January.
That 3 week period seems to be back again for weather etc
24th of January
Preparing to Frac.
Judging by this it will be mid Febuary until we know about 9M.
Well 9E.
Thi one looks like it took about 2 week taking weather etc into consideration----
19th December
Well 9E -They were getting the site ready for drilling.
28th December
3000ft drilled to date
24th of January
Has completed drilling down to 9400ft
The big one that we are all waiting for---
Horizontal -5H
28TH January 24, 2012
Completing planning stage
- Forums
- ASX - By Stock
- GGP
- today vs plan
today vs plan , page-4
-
- There are more pages in this discussion • 2 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)