    It aint clockwork, but i suppose it aint indoors, we cant control the weather or how hard the ground is ---

    WELL 6H
    9th October
    Spudded

    7th Nov
    Was getting ready to be fracced.

    Basically a 2-3 week drill period in this one.

    30th November
    6H had been Fracced, 1800 bbls of the 12750 bbls of fracc fluid had been recovered under the wells own pressure, a pump was being used to recover the remainder; oil and gas had been flowing to the surface in advance of any hydrocarbon returns

    Another 3 weeks to Fracc the well.

    14th December
    The well has been completed and is shut down while permanent production facilities are installed.


    19TH DEC
    well 6H is having permant production equipment installed after fraccing had finished and the initial flow rates were 379 barrels per day. The surface pumps were being installed that week and a gas pipeline agreement was being negotiated.

    28th December
    Permanent equipment is now installed. Waiting on gas pipeline construction.

    Some posters were nearly expecting the gas line to go in
    within a couple of days, a few posts later we had it up to a couple of weeks, plus holidays, then the bad weather and then--

    BINGO -

    24th of January.
    Gas pipeline has been completed & this 300+ barrel and Gas rich baby goes into production this week.

    Well 8A

    23rd October
    8A was spudded

    30th October
    Drilling completed to 9400ft. This one was drilled in a week.

    It was a months later....

    30th of November
    8A was preparing to be fracced.

    fracing took 2 weeks and then another 3 to completely unload going by their announcements----

    12th December
    Hydraulic fraccing had been completed and a service rig was due in within a few days to drill out the plugs separation each frac interval; then they would put the well into production to return the frac fluids and begin production testing, good production levels were antisipated and as good as the first well due to electrical log information and oil flowing to the surface during drilling phase

    19th Dec

    Well 8A has completed fraccing and is unloading 28 barrels of frac fluid per hour.


    28th of December
    Fraccing has been completed & oil has come to the surface during frac fluid recovery.

    Must have been substantial delays with weather and new years cos------


    24th December – still unloading Frac fluid, and oil has broken through at 109 bars per day(this well was showing up oil during the drilling stage as per 12th December


    Well 9M.

    It took over 2 weeks to drill this one-

    10th of December

    Spuded & by the 12th of december they were down 580 ft at which time they antisipated 8 days to gat to the targeted 9400 feet.

    14th December
    It was down 3300 feet

    19th December
    Well 9M - drilling was still being done, they were 8000 feet through to the targeted 9000 feet.

    28th December.
    Drilling to target depth of 9500 ft has been completed. Preparing to frac during the second week of January.

    That 3 week period seems to be back again for weather etc


    24th of January
    Preparing to Frac.

    Judging by this it will be mid Febuary until we know about 9M.

    Well 9E.

    Thi one looks like it took about 2 week taking weather etc into consideration----

    19th December
    Well 9E -They were getting the site ready for drilling.
    28th December
    3000ft drilled to date

    24th of January
    Has completed drilling down to 9400ft


    The big one that we are all waiting for---

    Horizontal -5H
    28TH January 24, 2012
    Completing planning stage
 