PYM pryme energy limited

7th SeptThe Deshotels 20-H No.1 well in the Turner Bayou Chalk...

  1. 116 Posts.
    7th Sept
    The Deshotels 20-H No.1 well in the Turner Bayou Chalk project is currently at a depth of 16,004 feet
    (4,878 metres). The targeted Austin Chalk formation has been intersected as anticipated and drilling is
    continuing to a depth of 16,400 feet (5,000 metres). The well-bore will be logged and evaluated prior to
    plugging back to the directional drilling kick-off point above the Austin Chalk.


    9th Sept
    Directors buying

    14th Sept
    The vertical section of the Deshotels 20-H No.1 well in the Turner Bayou Chalk project has reached total
    depth of 16,400 feet (5,000 metres). A full set of logs has been run and is being evaluated prior to the
    kick off of directional drilling to establish the start of the horizontal leg
    Logging has confirmed the full section of the Austin Chalk formation as interpreted from the mud log and
    the 3D seismic survey. Several other formations of interest will be evaluated in due course.

    So, how long did it take to drill the 396 feet to total depth from the 7th Sept?
    Since the Austin Chalk had been reached on the 7th the "Several other formations of interest" mentioned on the 14th (but not on the 7th)had been drilled through before the 7th.

    Interesting!
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.